DOC - Permit Finaled | | | 5/8/2020 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 5/8/2020 | | DONE |
|
|
|
|
BLD-Final | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by kevin debelloy
|
FIRE-Final Inspection | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Jim Page
|
|
|
Permit for hood suppression is finaled, final inspection for life fire safety is complete.
|
Fees Due Hold | 4/21/2020 | | 4/21/2020 | | DONE |
|
|
|
|
BLD-Final | 4/19/2020 | 4/20/2020 | 4/20/2020 | P | CANC |
Tony Young
|
|
|
>> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
|
FIRE-Final Inspection | 4/19/2020 | 4/20/2020 | 4/20/2020 | A | FAIL |
Jim Page
|
|
|
FIR permit for commercial hood fire suppression system must be finaled before life fire safety inspection can be complete, hood suppression inspection resulted in a failure, notes entered under FIR20-00140., a re-inspection fee has been added to permit due too 2 failures on permit. Inspection requested via web by kevin debelloy
|
FIRE-Final Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
|
BLD-Final | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
|
FIRE-Final Inspection | 4/9/2020 | 4/14/2020 | 4/14/2020 | A | FAIL |
Jim Page
|
|
|
FIR permit (FIR20-00140) for hood suppression system needs to be finaled before life fire safety can be completed.
Inspector please call 30 minutes before arrival Phone #: ###-#### Inspection requested via web by kevin debelloy
|
BLD-Framing/Rough-in | 4/9/2020 | 4/13/2020 | 4/13/2020 | A | DONE |
Tony Young
|
|
|
Inspector please call 30 minutes before arrival Phone #: ###-#### Inspection requested via web by kevin debelloy// nothing needed per contractor and engineer
|
BLD-Final | 4/9/2020 | 4/13/2020 | 4/9/2020 | P | CANC |
Tony Young
|
|
|
Inspector please call 30 minutes before arrival Phone #: ###-#### >> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
|
CHANGE STATUS TO (ISS) | | | 3/27/2020 | | DONE |
|
|
|
plan mod
|
Telephone call | | | 3/26/2020 | | DONE |
|
|
|
Emailed GC the 306 form to update the values for this plan mod.
|
Plan assigned to (JG) | 3/12/2020 | 3/12/2020 | 3/25/2020 | | PASS |
Javier Guzman
|
|
|
03/20 Plan Mod Gyro Shack ePlan
|
Routing - PLAN CHECK | 3/17/2020 | | 3/25/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Environmental | 3/17/2020 | | 3/25/2020 | | PASS |
Zach Conde
|
|
|
Signed off in ePlan by PW Enviormental Zach Conde-NOTE FROM ZACH-This one we failed back in December for not having grease abatement. They submitted GT specs directly to me. Passed on ePlan with this comment:
|
Permit Ready to Issue | | | 3/25/2020 | | DONE |
|
|
|
*PLAN MOD - DO NOT REISSUE**
Need
Revised Value (Plan mod application states the value is being affected)
|
Routing - FIRE | 3/17/2020 | 3/17/2020 | 3/24/2020 | | PASS |
Erika Akin
|
|
|
Plan Mod to relocate kitchen equipment. No change to previous comments.
|
Routing - MECHANICAL | 3/17/2020 | | 3/20/2020 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 3/17/2020 | | 3/17/2020 | | PASS |
Rita DeYoung
|
|
|
|
BLD-Conference | 3/12/2020 | 3/12/2020 | 3/12/2020 | P | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by kevin debelloy
|
Plan Modification Accepted | | | 3/12/2020 | | DONE |
|
|
|
adjustment to hood location for ADA egress clearance at hood
|
Release Hold on Job | | | 1/27/2020 | | DONE |
|
|
|
waiting for signed permit
|
Telephone call | | | 1/27/2020 | | DONE |
|
|
|
Emailed a reminder to the GC and applicant that we still need the permit to be signed before we can release the approved plans.
|
Issue PAID IN FULL permit | | | 1/23/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/23/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 11/20/2019 | 11/20/2019 | 12/13/2019 | | PASS |
Javier Guzman
|
|
|
12/19 2nd rev comp, 12/02 L2 Gyro Shack ePlan, pend PW envior
|
Routing - PLAN CHECK | 12/13/2019 | | 12/13/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Environmental | 12/13/2019 | | 12/13/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by PW Pre-Treatment Zach Conde
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/13/2019 | | DONE |
|
|
|
all met: jeff@hatchda.com
Need
GC Form
Revised Cert of Value
|
Route to Impact Fee Review | 12/4/2019 | 12/7/2019 | 12/5/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 11/20/2019 | | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - C.D.H | 11/20/2019 | | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by Central District Health Department Scott Paradis
|
1st review completed | | | 12/4/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 11/20/2019 | 11/20/2019 | 12/3/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 11/20/2019 | | 11/25/2019 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 11/20/2019 | | 11/20/2019 | | PASS |
Morgan Webb
|
|
|
NO ADDITION OF CUSTOMER SERVICE AREA
|
Routing - Addressing | 11/20/2019 | | 11/20/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Environmental | 11/20/2019 | | 11/20/2019 | | FAIL |
Rick Christenson
|
|
|
No grease abatement shown. Suitable and adequate grease abatement must be provided. Contact Zach Conde ###-####
|
Routing - Design Review | 11/20/2019 | | 11/20/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Intake Approval | | | 11/19/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 9/11/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following per checklist:
• Per checklist mechanical plans are required stamped and signed by an Idaho licensed engineer.
• With the new 839 lbs. MAU provide engineering calculations to show existing roof can support the new equipment load
• Provide DR letter of approval for the new exterior rooftop equipment or provide email transcript stating no approval letter is required.
|
Application received | | | 9/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 7 2019 1:20PM
|