BLD-Other | 12/26/2019 | 12/27/2019 | 12/27/2019 | A | PASS |
Brandon Shaw
|
|
|
Carport framing complete. Electrical inspection also submitted by Szurgot for the morning as well. Hope you can do both while you are there. Client will be home. Thank you! Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
DOC - Permit Finaled | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 11/26/2019 | 11/27/2019 | 11/27/2019 | A | PASS |
Tell Riley
|
|
|
Inspection in mudroom addition. Insulation R-20 spray in. Also please check framing in carport beam. OK to cover? Could we please get inspection before 9am? if not could inspector please call ###-#### Tara Thank you! Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
BLD-Framing/Rough-in | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
Jim Storey
|
|
|
Framing inspection please. Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
BLD-Wall Bracing | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Jim Storey
|
|
|
Sheer inspection Friday morning please Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
Plan resubmittals received | | | 10/21/2019 | | DONE |
|
|
|
engineer packet for car port. taken to josh
|
BLD-Foundation | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PASS |
Brandon Shaw
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 9/24/2019 | 9/25/2019 | 9/25/2019 | A | PASS |
Jim Storey
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 9/20/2019 | 9/23/2019 | 9/23/2019 | P | CANC |
Jim Storey
|
|
|
pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/18/2019 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 9/13/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 9/13/2019 | 9/13/2019 | 9/13/2019 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 9/13/2019 | | 9/13/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 9/13/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 9/13/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/13/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy yes
|
Permit Ready to Issue | | | 9/13/2019 | | DONE |
|
|
|
|
Application received | | 9/13/2019 | | | |
|
|
|
|