BLD-Final | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Jim Storey
|
|
|
SCREENED // Vince Phone #: ###-####
|
DOC - Permit Finaled | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 7/8/2020 | 7/8/2020 | 7/8/2020 | A | DONE |
Jim Storey
|
|
|
SCREENED // Vince Phone #: ###-#### 4.45
|
BLD-Energy code compliance | 4/24/2020 | 4/24/2020 | 4/24/2020 | P | PART |
Tell Riley
|
|
|
Vince Phone #: ###-####//energy ok per plan mod//still need to have apporved post attachments at front porch posts//windows in upstairs bath may need to be tempered, cant measure are gyp is blocking glass//
|
BLD-Framing/Rough-in | 4/24/2020 | 4/24/2020 | 4/24/2020 | P | PART |
Tell Riley
|
|
|
Vince Phone #: ###-####//framing corrections made//still need approved post attachment, approved by engineer or architect//document provided but is not stamped//
|
OVERRIDE | | | 4/24/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 4/20/2020 | 4/20/2020 | 4/24/2020 | | DONE |
Rob Patrick
|
|
|
Plan Mod ePlan
|
Routing - PLAN CHECK | 4/21/2020 | | 4/24/2020 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/24/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
CHANGE STATUS TO (ISS) | | | 4/24/2020 | | DONE |
|
|
|
|
Routing - MECHANICAL | 4/21/2020 | | 4/22/2020 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 4/20/2020 | | DONE |
|
|
|
corrections for insulation and manual j
|
BLD-Energy code compliance | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | FAIL |
Tell Riley
|
|
|
Vince Phone #: ###-####//F02 trusses still need bracing//girders still need nailed//verify R49 insulation values have been acheived--batts show R38//porch post attachment must be approved attachment and be protected from ground/concrete contact by approved methods//
|
BLD-Framing/Rough-in | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PART |
Tell Riley
|
|
|
vince - Screened for COVID 19 symptoms Phone #: ###-####///se plans and truss docs for corrections ok to insulate//
|
BLD-Framing/Rough-in | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | FAIL |
Tell Riley
|
|
|
Vence ** cleared** Phone #: ###-####//CN issued//previous wall bracing corrections have not been addressed//plans are missing 1/2 pages ripped some areas missing//need to provide engineering documents//previous corrections were marked in red on floors//complete inspection was not completed due to missing engineering/plans//
|
BLD-Wall Bracing | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PART |
Tell Riley
|
|
|
add straps above windows///need to install interior hold downs//provide engineers approval of lsl studs//provide fix for wrong hold downs used at courtyard//ok to wrap and install windows when exterior straps are nailed completely//CN left onsite with framer//exterior shear nailing ok//
|
BLD-Wall Bracing | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | CANC |
Tell Riley
|
|
|
Vince Phone #: ###-####
|
BLD-Wall Bracing | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | FAIL |
Tell Riley
|
|
|
Vince Phone #: ###-####//still need to install straping//portal frame still needed//CN still stands until all corrections made//site contact was informed to complete all corrections and call for re-inspection when complete//
|
BLD-Wall Bracing | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | FAIL |
Mike Jordan
|
|
|
Vince Phone #: ###-####. Provide 8d hot dipped galvanized nails into sill plate. Nail off all straps. Missing stdh 14 on interior wall. Missed portal frame on interior/exterior wall. needs to install all CMST16 straping and blocking over openeings as noted on wall bracing plans.
|
BLD-Footing | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | PART |
Tell Riley
|
|
|
Pat Phone #: ###-####//setbacks per plans//rebar in garage openings//will cover after pour//no frost observed in subgrade at time of inspection//
|
Issue PAID IN FULL permit | | | 12/18/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/5/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 12/5/2019 | | DONE |
|
|
|
met
|
Telephone call | | | 12/4/2019 | | DONE |
|
|
|
Emailed and left a voicemail for Vince to inform him I can not batch stamp this permit until the final values are submitted for BLD18-01628.
|
Routing - FIRE | 11/29/2019 | 11/29/2019 | 12/3/2019 | | PASS |
Lee G Meredith
|
|
|
12/12 (402) Kouba Homes
12-3-19 builder is installing a fire hydrant on the property that meets the required hydrant distance requirements and the driveway has been determined to be adequate to support fire apparatus. No sprinklers are required.
|
Plan assigned to (RDP) | 9/24/2019 | 9/24/2019 | 12/3/2019 | | DONE |
Rob Patrick
|
|
|
12/03 Failed...Smoke and CO detectors req'd
|
Routing - PLAN CHECK | 12/3/2019 | | 12/3/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2019 | | DONE |
Rob Patrick
|
|
|
|
Plan Reviewer's activity | | | 11/12/2019 | | DONE |
|
|
|
Ron Johnson informed me that sprinklers can be omitted if the builder has a fire hydrant installed on the property. There is a pressurized main that runs through the property that would allow for this. The builder has been informed of this option via email.
|
Routing - FIRE | 11/6/2019 | 11/6/2019 | 11/6/2019 | | FAIL |
Lee G Meredith
|
|
|
Access and hydrant distance exceed maximum allowed distance. Sprinkelrs are required. Applicant to resubmit with documentation indicating they will be provided.
Update 11-12-19: Per Ron Johnson, a pressureized main runs through the property and if the builder has a hydrant installed, sprinklers will not be required. This option was presented to the builder via email. He responded that he has inquired with SUEZ and will provide updates.
|
1st review completed | | | 11/6/2019 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLANNING | 9/24/2019 | | 11/6/2019 | | PASS |
Ethan Mansfield
|
|
|
Passed by LNL in ePlan, EOM is passing here.
|
Routing - PLAN CHECK | 9/24/2019 | | 11/6/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 9/24/2019 | | 9/26/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 9/24/2019 | 9/27/2019 | 9/25/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 9/24/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/24/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/24/2019 | | DONE |
|
|
|
|
Routing - Addressing | 9/24/2019 | | 9/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/24/2019 | | 9/24/2019 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 9/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 17 2019 9:17AM
|