BLD-Final | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | PASS |
Tell Riley
|
|
|
garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover
|
DOC - Permit Finaled | 5/8/2020 | 5/8/2020 | 5/8/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Blower Door Test Results | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | CANC |
Tell Riley
|
|
|
|
Plan Reviewer's activity | | | 3/12/2020 | | DONE |
Jenny Nelson
|
|
|
Manual J updated to reflect insulation values used during construction - ok to use 38 in attic, 21 in walls and .31 or better for fenestration JJN
|
Routing - MECHANICAL | 3/12/2020 | | 3/12/2020 | | PASS |
Troy James
|
|
|
Revised acca report
|
BLD-Final | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | NR |
Tell Riley
|
|
|
Garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//plans show R 49 attic insulation, tag show R38 installed//
|
BLD-Blower Door Test Results | 3/11/2020 | 3/11/2020 | 3/11/2020 | A | DONE |
Tell Riley
|
|
|
2.91 ACH 50
|
BLD-Other | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | PASS |
Tell Riley
|
|
|
Soffits//ok per plans//
|
BLD-Framing/Rough-in | 1/1/2020 | 1/2/2020 | 1/2/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//corrections made//
|
BLD-Energy code compliance | 1/1/2020 | 1/2/2020 | 1/2/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Framing/Rough-in | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//ok to insulate//check hangers at landing, and truss bracing//
|
BLD-Framing/Rough-in | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//correction notice posted//
|
BLD-Wall Bracing | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####
|
BLD-Foundation | 10/25/2019 | 10/28/2019 | 10/28/2019 | P | PART |
Tell Riley
|
|
|
wall... 2 if possible // Mark Phone #: ###-####//ok per plans//forman says blanket crew is on their way to cover//confirmed with Mark//
|
BLD-Footing | 10/24/2019 | 10/25/2019 | 10/25/2019 | P | PASS |
Tell Riley
|
|
|
about 2 it will be ready // mark Phone #: ###-####//per plans//
|
Inspection Record Card- Bld | | | 10/22/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/22/2019 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 10/15/2019 | 10/15/2019 | 10/15/2019 | | DONE |
Jenny Nelson
|
|
|
|
Plan assigned to (RDP) | 9/18/2019 | 9/18/2019 | 10/15/2019 | | DEFR |
Rob Patrick
|
|
|
10/01 sfd L1 ePlan
|
Routing - PLAN CHECK | 9/18/2019 | | 10/15/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 10/15/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 10/15/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/18/2019 | 9/21/2019 | 9/19/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 9/18/2019 | | 9/19/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/18/2019 | | 9/18/2019 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 9/18/2019 | | 9/18/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/18/2019 | | 9/18/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/18/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/18/2019 | | DONE |
|
|
|
|
Application received | | | 9/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 17 2019 10:26AM
|