Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-03659
StatusFinaled
Name ARMADA HOMES
Site Address 9656 W MACAW ST
Project NameEronel 14-1
Customer Number 
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 1964 sq. ft., two story (first story 1305 sq. ft., second story 659 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 79 sq. ft. of covered patio/porch and a 491 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/7/20205/8/20205/8/2020APASS
DetailsTell Riley
garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover
DOC - Permit Finaled5/8/20205/8/20205/8/2020PPASS
DetailsTell Riley
BLD-Blower Door Test Results5/7/20205/8/20205/8/2020ACANC
DetailsTell Riley
Plan Reviewer's activity  3/12/2020 DONE
DetailsJenny Nelson
Manual J updated to reflect insulation values used during construction - ok to use 38 in attic, 21 in walls and .31 or better for fenestration JJN
Routing - MECHANICAL3/12/2020 3/12/2020 PASS
DetailsTroy James
Revised acca report
BLD-Final3/10/20203/11/20203/11/2020ANR
DetailsTell Riley
Garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//plans show R 49 attic insulation, tag show R38 installed//
BLD-Blower Door Test Results3/11/20203/11/20203/11/2020ADONE
DetailsTell Riley
2.91 ACH 50
BLD-Other1/2/20201/2/20201/2/2020PPASS
DetailsTell Riley
Soffits//ok per plans//
BLD-Framing/Rough-in1/1/20201/2/20201/2/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//corrections made//
BLD-Energy code compliance1/1/20201/2/20201/2/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD-Framing/Rough-in12/27/201912/27/201912/27/2019PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//ok to insulate//check hangers at landing, and truss bracing//
BLD-Framing/Rough-in12/23/201912/24/201912/24/2019AFAIL
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//correction notice posted//
BLD-Wall Bracing11/25/201911/26/201911/26/2019APASS
DetailsTell Riley
Mark Phone #: ###-####
BLD-Foundation10/25/201910/28/201910/28/2019PPART
DetailsTell Riley
wall... 2 if possible // Mark Phone #: ###-####//ok per plans//forman says blanket crew is on their way to cover//confirmed with Mark//
BLD-Footing10/24/201910/25/201910/25/2019PPASS
DetailsTell Riley
about 2 it will be ready // mark Phone #: ###-####//per plans//
Inspection Record Card- Bld  10/22/2019 DONE
Issue PAID IN FULL permit  10/22/2019 DONE
Plan assigned to (J_N)10/15/201910/15/201910/15/2019 DONE
DetailsJenny Nelson
Plan assigned to (RDP)9/18/20199/18/201910/15/2019 DEFR
DetailsRob Patrick
10/01 sfd L1 ePlan
Routing - PLAN CHECK9/18/2019 10/15/2019 PASS
DetailsJenny Nelson
1st review completed  10/15/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  10/15/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  10/15/2019 DONE
Route to Impact Fee Review9/18/20199/21/20199/19/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL9/18/2019 9/19/2019 PASS
DetailsTroy James
Routing - PLANNING9/18/2019 9/18/2019 PASS
DetailsJeff Lowe
Routing - Addressing9/18/2019 9/18/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/18/2019 9/18/2019 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  9/18/2019 DONE
Intake Approval  9/18/2019 PASS
Recd Pcfee & Taken To Pln CK  9/18/2019 DONE
Application received  9/17/2019 DONE
Application submitted via PDS Online on Sep 17 2019 10:26AM