Permit Information
Permit NumberBLD19-03843
StatusFinaled
Name KEELEY ENTERPRISES INC
Site Address 4908 N ALLAMAR DR
Project NameRowley Remodel
Customer Number 
ePlanReviewYes
Description
Permit for a basement remodel, to include: new flooring, a sink in a storage room, updating the bathroom, and minor re-framing. All work per plans, notations, attachements, local codes & ordinances. Separate electrical & plumbing permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/14/20202/18/20202/18/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Brian Keeley//corrections made//
DOC - Permit Finaled2/18/20202/18/20202/18/2020PPASS
DetailsTell Riley
BLD-Final2/7/20202/10/20202/10/2020ANR
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Brian Keeley//will need to add smoke detectors upstairs, and a smoke CO combo outside upstairs bedrooms, interconnected to downstairs//return handrails to wall//
BLD-Wall cover11/13/201911/13/201911/13/2019PPASS
DetailsTell Riley
Inspection requested via web by Brian Keeley
BLD-Framing/Rough-in10/31/201911/1/201911/1/2019ANR
DetailsTell Riley
Please call ahead for access. Phone #: ###-#### Inspection requested via web by Brian Keeley//need plumbing and electrical//
Plan assigned to (JAB) Josh10/21/201910/21/201910/31/2019 PASS
DetailsJosh Bogle
10/25 remodel, ePlan - 1st done
Routing - PLAN CHECK10/31/2019 10/31/2019 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  10/31/2019 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  10/31/2019 DONE
met
Issue PAID IN FULL permit  10/31/2019 DONE
Inspection Record Card- Bld  10/31/2019 DONE
Routing - PLAN CHECK10/28/2019 10/28/2019 PASS
DetailsJosh Bogle
Beam innadequate
Routing - PLAN CHECK10/21/2019 10/25/2019 FAIL
DetailsJosh Bogle
1st review completed  10/25/2019 FAIL
DetailsJosh Bogle
Telephone call  10/21/2019 DONE
applicant called in and will not be submitting this as an ADU, he will not add a full kitchen.
Plans ACCEPTED BY PLAN TECH  10/21/2019 DONE
Intake Approval  10/21/2019 PASS
Recd Pcfee & Taken To Pln CK  10/21/2019 DONE
Intake Approval  10/17/2019 FAIL
ADU must be approved by planning and zoning prior to submittal for the building permit
Telephone call  10/17/2019 DONE
Spoke with Brian regarding approval from Planning and Zoning before submitting application for ADU
Intake Approval  10/15/2019 FAIL
We are unable to use JPG files. Please upload them as PDF Files. If you have questions on our submittal standards, please use the link below.
https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
-You can always come into our office and submit if you are unable to do PDF files.
(Please delete the JPG files if they want to contiune with eplan)
Intake Approval  10/2/2019 FAIL
Please upload the before and after drawings, I removed the 2 drawing because it was upside down so please upload again so it faces the correct way. Please make sure to have the drawings as complete as possible so we can do our plan reviews
Application received  9/27/2019 DONE
Application submitted via PDS Online on Sep 27 2019 1:48PM