BLD-Final | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Keeley//corrections made//
|
DOC - Permit Finaled | 2/18/2020 | 2/18/2020 | 2/18/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Keeley//will need to add smoke detectors upstairs, and a smoke CO combo outside upstairs bedrooms, interconnected to downstairs//return handrails to wall//
|
BLD-Wall cover | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | PASS |
Tell Riley
|
|
|
Inspection requested via web by Brian Keeley
|
BLD-Framing/Rough-in | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | NR |
Tell Riley
|
|
|
Please call ahead for access. Phone #: ###-#### Inspection requested via web by Brian Keeley//need plumbing and electrical//
|
Plan assigned to (JAB) Josh | 10/21/2019 | 10/21/2019 | 10/31/2019 | | PASS |
Josh Bogle
|
|
|
10/25 remodel, ePlan - 1st done
|
Routing - PLAN CHECK | 10/31/2019 | | 10/31/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 10/31/2019 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 10/31/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/31/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/28/2019 | | 10/28/2019 | | PASS |
Josh Bogle
|
|
|
Beam innadequate
|
Routing - PLAN CHECK | 10/21/2019 | | 10/25/2019 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 10/25/2019 | | FAIL |
Josh Bogle
|
|
|
|
Telephone call | | | 10/21/2019 | | DONE |
|
|
|
applicant called in and will not be submitting this as an ADU, he will not add a full kitchen.
|
Plans ACCEPTED BY PLAN TECH | | | 10/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/21/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/17/2019 | | FAIL |
|
|
|
ADU must be approved by planning and zoning prior to submittal for the building permit
|
Telephone call | | | 10/17/2019 | | DONE |
|
|
|
Spoke with Brian regarding approval from Planning and Zoning before submitting application for ADU
|
Intake Approval | | | 10/15/2019 | | FAIL |
|
|
|
We are unable to use JPG files. Please upload them as PDF Files. If you have questions on our submittal standards, please use the link below.
https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
-You can always come into our office and submit if you are unable to do PDF files.
(Please delete the JPG files if they want to contiune with eplan)
|
Intake Approval | | | 10/2/2019 | | FAIL |
|
|
|
Please upload the before and after drawings, I removed the 2 drawing because it was upside down so please upload again so it faces the correct way. Please make sure to have the drawings as complete as possible so we can do our plan reviews
|
Application received | | | 9/27/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2019 1:48PM
|