BLD-Aging Inspection | 2/26/2020 | 2/26/2020 | 2/27/2020 | | DONE |
Tell Riley
|
|
|
no contact since footing inspection//
|
BLD-Aging Inspection | 2/25/2020 | 2/25/2020 | 2/26/2020 | | CANC |
Tell Riley
|
|
|
|
BLD-Footing | 10/11/2019 | 10/14/2019 | 10/14/2019 | A | PART |
Tell Riley
|
|
|
Phone #: ###-####//footing depth ok//setbacks were reduced from site plans to 6+ feet--zoning review allows 5 ft side setback--all other setbacks same as siteplan//no posts set at time of inspection//ok to set posts and pour footings//
|
Routing Walk-In (Zoning) | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Ethan Mansfield
|
|
|
CZC19-00210 approved by SL.
|
Routing Walk-In (BLD) | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/1/2019 | | 10/1/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 10/1/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/1/2019 | | DONE |
|
|
|
|
Application received | | 10/1/2019 | | | |
|
|
|
|