BLD-Final | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | PASS |
Jim Storey
|
|
|
Access code on garage is 1969. Please call 1 hour prior to coming. Thank you. Phone #: ###-#### Inspection requested via web by Jeffery Thompson
|
DOC - Permit Finaled | 7/7/2020 | 7/7/2020 | 7/7/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | PASS |
Brandon Shaw
|
|
|
OK to cover...
|
BLD-Wall cover | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | CANC |
Brandon Shaw
|
|
|
Not sure if this is the correct inspection request--Wall cover--for obtaining approval to hang sheetrock---I just wanted to make sure that I requested all the items needed to progress into drywall. Thank you for your understanding--Please call Phone #: ###-#### Inspection requested via web by Jeffery Thompson
|
BLD-Framing/Rough-in | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jeffery Thompson
|
BLD-Wall Bracing | 2/27/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Brandon Shaw
|
|
|
Jeremy Phone #: ###-####
|
Routing - MECHANICAL | 2/24/2020 | | 2/24/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Conference | 2/6/2020 | 2/6/2020 | 2/6/2020 | P | DEFR |
Brandon Shaw
|
|
|
Concerned neighbor called about premature work... work in procceding accordingly.
|
BLD-Foundation | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 1/24/2020 | 1/24/2020 | 1/24/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Conference | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Footing | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes // canceled by wes
|
Telephone call | | | 1/13/2020 | | DONE |
|
|
|
Emailed GC/applicant to inform them that not all of the fees have been paid on this project and once they have been paid we can issue the permits.
|
Issue PAID IN FULL permit | | | 1/13/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/13/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/2/2020 | | |
|
|
|
|
Plan assigned to (BJM) | 12/16/2019 | 12/16/2019 | 1/2/2020 | | DONE |
Brian McGowan
|
|
|
12/27- 1st Review Complete-Need Planning Approva- L1 SFD ePlan
|
Routing - PLANNING | 1/2/2020 | | 1/2/2020 | | PASS |
Sue Cummings
|
|
|
Shed is NOT part of the permit
|
Permit Ready to Issue | | | 1/2/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 12/27/2019 | | DONE |
Brian McGowan
|
|
|
Emailed Jeff asking for the ICC-ES Report or Intertek Report on the spray foam he is using. If he doen't reply I will send it back in ePlan.
|
Routing - PLAN CHECK | 12/27/2019 | | 12/27/2019 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/27/2019 | | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 12/19/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 12/16/2019 | | 12/19/2019 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 12/16/2019 | 12/19/2019 | 12/17/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 12/16/2019 | | 12/17/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/16/2019 | | 12/16/2019 | | DONE |
Sue Cummings
|
|
|
Need to know how tall the shed is please.
|
Routing - Addressing | 12/16/2019 | | 12/16/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/16/2019 | | 12/16/2019 | | PASS |
Candy A. Nichols
|
|
|
NO CREDIT FOR HOUSE MOVE-NEVER CONNECTED TO SEWER
|
Intake Approval | | | 12/16/2019 | | FAIL |
|
|
|
Please provide the installation information for your conditional crawlspace.
|
Intake Approval | | | 12/16/2019 | | FAIL |
|
|
|
the corrections were added with new names so they did not version over, they were deleted and spoke with Jeff to inform him to name the same so that they can version over.
|
Recd Pcfee & Taken To Pln CK | | | 12/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 12/16/2019 | | PASS |
|
|
|
|
Intake Approval | | | 12/13/2019 | | FAIL |
|
|
|
1. Plans must be uploaded as individual sheets.
2. File names need to include first characters of the discipline name.
3. Call out on drawing plans location of - crawl space, attic acess and mechanical equipment location.
|
Meeting | | | 12/13/2019 | | DONE |
|
|
|
GC needs to be verify, number listed on application does not show the state website and the one on on directory does not have an RCE or RCT/// updated 12/16/19 TCH. Found RCE number on states website
|
Application received | | | 12/12/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 12 2019 9:28PM
|