Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-04836
StatusFinaled
Name THOMPSON HOMES INC
Site Address 460 E SCHMEIZER LN
Project NameBerman Ackler Residence
Customer Number 
ePlanReviewYes
Description
RESCHECK USED FOR ENERGY COMPLIANCE- 1" SPRAY FOAM ADDED TO EXTERIOR WALLS- SHED IS NOT PART OF THIS PERMIT- Permit for the construction of a new 2096 sq. ft., one story single family dwelling with 3 bedrooms, 3 bathrooms, approximately 636 sq. ft. of covered patio/porch and a 1471 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. REScheck provided for Energy Compliance. ***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/6/20207/7/20207/7/2020APASS
DetailsJim Storey
Access code on garage is 1969. Please call 1 hour prior to coming. Thank you. Phone #: ###-#### Inspection requested via web by Jeffery Thompson
DOC - Permit Finaled7/7/20207/7/20207/7/2020PPASS
DetailsJim Storey
BLD-Energy code compliance3/31/20204/1/20204/1/2020APASS
DetailsBrandon Shaw
OK to cover...
BLD-Wall cover3/31/20204/1/20204/1/2020ACANC
DetailsBrandon Shaw
Not sure if this is the correct inspection request--Wall cover--for obtaining approval to hang sheetrock---I just wanted to make sure that I requested all the items needed to progress into drywall. Thank you for your understanding--Please call Phone #: ###-#### Inspection requested via web by Jeffery Thompson
BLD-Framing/Rough-in3/25/20203/26/20203/26/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Jeffery Thompson
BLD-Wall Bracing2/27/20202/28/20202/28/2020PPASS
DetailsBrandon Shaw
Jeremy Phone #: ###-####
Routing - MECHANICAL2/24/2020 2/24/2020 PASS
DetailsTroy James
Resubmitted manual j report
BLD-Conference2/6/20202/6/20202/6/2020PDEFR
DetailsBrandon Shaw
Concerned neighbor called about premature work... work in procceding accordingly.
BLD-Foundation1/28/20201/29/20201/29/2020PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing1/24/20201/24/20201/24/2020APASS
DetailsJim Storey
Phone #: 2088708888 >> Inspection requested via mobile web by Wes
BLD-Conference1/22/20201/23/20201/23/2020PCANC
DetailsBrandon Shaw
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
BLD-Footing1/22/20201/23/20201/23/2020PCANC
DetailsBrandon Shaw
As late as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes // canceled by wes
Telephone call  1/13/2020 DONE
Emailed GC/applicant to inform them that not all of the fees have been paid on this project and once they have been paid we can issue the permits.
Issue PAID IN FULL permit  1/13/2020 DONE
Inspection Record Card- Bld  1/13/2020 DONE
OVERRIDE  1/2/2020  
Plan assigned to (BJM)12/16/201912/16/20191/2/2020 DONE
DetailsBrian McGowan
12/27- 1st Review Complete-Need Planning Approva- L1 SFD ePlan
Routing - PLANNING1/2/2020 1/2/2020 PASS
DetailsSue Cummings
Shed is NOT part of the permit
Permit Ready to Issue  1/2/2020 DONE
Plan Reviewer's activity  12/27/2019 DONE
DetailsBrian McGowan
Emailed Jeff asking for the ICC-ES Report or Intertek Report on the spray foam he is using. If he doen't reply I will send it back in ePlan.
Routing - PLAN CHECK12/27/2019 12/27/2019 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  12/27/2019 DONE
DetailsBrian McGowan
1st review completed  12/19/2019 FAIL
DetailsBrian McGowan
Routing - PLAN CHECK12/16/2019 12/19/2019 FAIL
DetailsBrian McGowan
Route to Impact Fee Review12/16/201912/19/201912/17/2019 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL12/16/2019 12/17/2019 PASS
DetailsTroy James
Routing - PLANNING12/16/2019 12/16/2019 DONE
DetailsSue Cummings
Need to know how tall the shed is please.
Routing - Addressing12/16/2019 12/16/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/16/2019 12/16/2019 PASS
DetailsCandy A. Nichols
NO CREDIT FOR HOUSE MOVE-NEVER CONNECTED TO SEWER
Intake Approval  12/16/2019 FAIL
Please provide the installation information for your conditional crawlspace.
Intake Approval  12/16/2019 FAIL
the corrections were added with new names so they did not version over, they were deleted and spoke with Jeff to inform him to name the same so that they can version over.
Recd Pcfee & Taken To Pln CK  12/16/2019 DONE
Intake Approval  12/16/2019 PASS
Intake Approval  12/13/2019 FAIL
1. Plans must be uploaded as individual sheets.
2. File names need to include first characters of the discipline name.
3. Call out on drawing plans location of - crawl space, attic acess and mechanical equipment location.
Meeting  12/13/2019 DONE
GC needs to be verify, number listed on application does not show the state website and the one on on directory does not have an RCE or RCT/// updated 12/16/19 TCH. Found RCE number on states website
Application received  12/12/2019 DONE
Application submitted via PDS Online on Dec 12 2019 9:28PM