BLD-Framing/Rough-in | 8/6/2020 | 8/7/2020 | 8/7/2020 | P | PASS |
Jim Storey
|
|
|
Requesting PM inspection for framing. Please call 30 minutes prior to meet at gate 50 to be escorted. Thanks!
Frank Phone #: ###-#### Inspection requested via web by Frank Loucks exterior wall ok
|
BLD-Concrete | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PART |
Jim Storey
|
|
|
Requesting inspection for a concrete/rebar ramp at Gate C8A for a 11:00AM concrete pour. Call 30 minutes prior to be escorted to job site MTI will be on site to witness the epoxy of smooth dowels and rebar. Thanks! Phone #: ###-#### Inspection requested via web by Frank Loucks // si on site pending report.
|
BLD-Foundation | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PASS |
Jim Storey
|
|
|
Requesting to call 30 min prior to meet at gate 50 to be escorted in SIDA badge area. Thanks! Phone #: ###-#### Inspection requested via web by Frank Loucks pending si report
|
BLD-Foundation | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PEND |
Dave Hannah
|
|
|
Please call before coming so I can meet you at gate 50 to be escorted into the job site. If you don''t know where gat 50 is, call me so I can you give directions Thanks! Phone #: ###-#### Inspection requested via web by Frank Loucks ok after spec inspection sign off
|
Telephone call | | | 7/1/2020 | | DONE |
|
|
|
Let him know of the new COV and new fees.
|
CHANGE STATUS TO (ISS) | | | 7/1/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 6/23/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 6/23/2020 | | DONE |
|
|
|
MET NEW REVISED VALUE FOR MOD
PLAN MOD
|
Plan assigned to (M_H) | 5/22/2020 | | 6/22/2020 | | DONE |
Michael Hanson
|
|
|
06/02 Plan Mod - Airport bridge - Structural update
|
Routing - PLAN CHECK | 5/28/2020 | | 6/22/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 5/28/2020 | | 6/22/2020 | | PASS |
Michael Hanson
|
|
|
AHJ
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 5/22/2020 | 5/25/2020 | 5/27/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 5/22/2020 | | DONE |
Christina Prado
|
|
|
Relocate fixed walkway - Will need new COV
|
Issue & PRINT permit | | | 3/9/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/9/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/2/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 3/2/2020 | | DONE |
|
|
|
ALL MET
Need
GC Form
Revised Cert of Value
(if city of boise is paying for fees, please have them email the JV account)
|
Plan assigned to (M_H) | 1/10/2020 | | 3/2/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 02/10 #502 L3 ePlan - Airport Walkway Gate C8A
|
Routing Off Site - STRUCTURAL | 2/24/2020 | | 3/2/2020 | | PASS |
Michael Hanson
|
|
|
AHJ
|
1st review completed | | | 2/10/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 1/10/2020 | | 2/10/2020 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required by AHJ engineering.
|
Routing - PLAN CHECK | 1/10/2020 | | 2/10/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - FIRE | 1/10/2020 | 1/10/2020 | 2/3/2020 | | PASS |
Erika Akin
|
|
|
No comments attached. PDS Fire to verify life safety.
|
Routing - PLANNING | 1/10/2020 | | 1/15/2020 | | PASS |
Nicolette Womack
|
|
|
Exterior changes as per Design Review approval.
|
Routing - PLUMBING | 1/10/2020 | | 1/14/2020 | | PASS |
Daryl Spivey
|
|
|
No plumbing review required
|
Routing PW Drainage | 1/10/2020 | | 1/10/2020 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 1/10/2020 | | 1/10/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2020 | | 1/10/2020 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING FIXTURES.
|
Routing - Erosion and Sediment | 1/10/2020 | | 1/10/2020 | | PASS |
Michael Zawacki
|
|
|
Waiver approved
|
Routing - Design Review | 1/10/2020 | | 1/10/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Intake Approval | | | 12/31/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/27/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• On the uploaded 310 form provide owners or design professionals signature and date
• Provide DR/Planning & Zoning letters of approval for the exterior work.
|
Application received | | | 12/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 20 2019 3:37PM
|