BLD-Aging Inspection | 7/9/2020 | 7/9/2020 | 7/10/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Tony Young
|
|
|
Quant Phone #: ###-####
|
BLD-Energy code compliance | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Tony Young
|
|
|
Quant Phone #: ###-####
|
BLD-Framing/Rough-in | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PASS |
Tony Young
|
|
|
Quint Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 2/21/2020 | 2/24/2020 | 2/24/2020 | P | NR |
Tony Young
|
|
|
Quint Phone #: ###-####,, needs electrical 1st
|
BLD-Framing/Rough-in | 2/21/2020 | 2/21/2020 | 2/21/2020 | P | NR |
Tony Young
|
|
|
Quint Phone #: ###-####// needs electrical 1st
|
BLD-Framing/Rough-in | 2/19/2020 | 2/21/2020 | 2/21/2020 | A | NR |
Tony Young
|
|
|
Quint Phone #: ###-####,, needs electrical
|
BLD-Framing/Rough-in | 2/19/2020 | 2/19/2020 | 2/20/2020 | P | PART |
Tony Young
|
|
|
Quint Phone #: ###-####,, walk through only,, needs trades 1st,, exterior ok to cover
|
Routing Walk-In (BLD) | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | DONE |
Josh Bogle
|
|
|
has additional documents
|
Plan assigned to (JAB) Josh | 1/21/2020 | 1/21/2020 | 2/5/2020 | | PASS |
Josh Bogle
|
|
|
01/27 addition, ePlan - 1st done
|
Routing - PLAN CHECK | 2/5/2020 | | 2/5/2020 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 2/5/2020 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 2/5/2020 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/5/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2020 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy yes
|
Permit Ready to Issue | | | 2/5/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/5/2020 | | DONE |
|
|
|
|
Telephone call | | | 2/5/2020 | | DONE |
|
|
|
plans were left on my desk, left message to Jeb to come and pick them up
|
Telephone call | | | 1/31/2020 | | DONE |
|
|
|
applicant was inform that it be better to do paper plans, email send to Tisha for Eplan
|
Intake Approval | | | 1/31/2020 | | PASS |
|
|
|
Josh this went from Eplan to Paper plans, I have set them on your desk j.a
|
Routing Walk-In (BLD) | 1/29/2020 | 1/29/2020 | 1/29/2020 | A | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 1/24/2020 | 1/24/2020 | 1/24/2020 | P | FAIL |
Josh Bogle
|
|
|
discussed the needed structural, insulation, and sprinkler info
|
Routing - PLAN CHECK | 1/21/2020 | | 1/22/2020 | | FAIL |
Josh Bogle
|
|
|
incomplete plans
|
Routing - PLANNING | 1/21/2020 | | 1/22/2020 | | PASS |
Sue Cummings
|
|
|
|
1st review completed | | | 1/22/2020 | | FAIL |
Josh Bogle
|
|
|
|
Intake Approval | | | 1/21/2020 | | PASS |
|
|
|
|
Intake Approval | | | 1/16/2020 | | FAIL |
|
|
|
Site plan-Show location of the structure including balconies, decks, driveways, and walkways with dimensions and distances to the property lines.
|
Application received | | | 1/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 6 2020 10:50AM
|