BLD-Foundation | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PART |
Tell Riley
|
|
|
Stem Wall ispection. Tell, we have mud at 10:30, I will push it back if you can make it but please try to come before then. Thank you. Phone #: ###-#### Inspection requested via web by Shawn Plimmer//rebar ok per plans//vents will need vent wells due to elevations//contractor will submit updated site plan, changes due to meet rear setbacks//WIP//
|
BLD-Footing | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PART |
Tell Riley
|
|
|
3pm or around there please. Call Shawn on the way there. ###-#### Phone #: ###-#### Inspection requested via web by Shawn Plimmer//building appears to be within setbacks, was moved forward 7 inches to meet rear setbacks//contractor will submit plan modificaiton for adjusted site plan//rebar appears to be per the plan//
|
BLD-Conference | 7/30/2020 | 7/31/2020 | 7/31/2020 | P | DONE |
Tell Riley
|
|
|
Please call shawn at 2088013772 20 minutes prior to inspection. Phone #: ###-#### Inspection requested via web by Shawn Plimmer
|
Issue PAID IN FULL permit | | | 7/23/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/23/2020 | | DONE |
|
|
|
|
Telephone call | | | 6/29/2020 | | DONE |
|
|
|
Emailed GC and appliant to inform them we still need something from ACHD to know if fees are due and if an inspection is required.
|
Telephone call | | | 6/22/2020 | | DONE |
|
|
|
sent email about expiring permit
|
Telephone call | | | 6/17/2020 | | DONE |
|
|
|
emailed Jeff to let him know that we still needed information from ACHD regarding fees and inspections before we could issue.
|
OVERRIDE | | | 5/14/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 5/14/2020 | | DONE |
|
|
|
met:
Need ACHD
Need RP
Need GC
Need Revised Value
|
Routing - PLAN CHECK | 5/13/2020 | | 5/13/2020 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2020 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 3/5/2020 | | 5/13/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 04/14 #502 L3 ePlan - Loop Technologies
|
Routing Off Site - STRUCTURAL | 5/7/2020 | | 5/12/2020 | | PASS |
Michael Hanson
|
|
|
per Sydney Gold @ KPFF
|
Routing - FIRE | 5/11/2020 | 5/11/2020 | 5/11/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - Design Review | 5/8/2020 | | 5/8/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 4/15/2020 | 4/18/2020 | 4/15/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/5/2020 | 3/5/2020 | 4/15/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
1st review completed | | | 4/15/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 3/5/2020 | | 4/14/2020 | | FAIL |
Michael Hanson
|
|
|
KPFF
|
Routing - PLAN CHECK | 3/5/2020 | | 4/14/2020 | | FAIL |
Michael Hanson
|
|
|
See buiding plan review report in ePlan for corrections required.
|
Routing - MECHANICAL | 3/5/2020 | | 3/13/2020 | | PASS |
Troy James
|
|
|
|
Routing PW Solid Waste | 3/6/2020 | | 3/11/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLUMBING | 3/5/2020 | | 3/10/2020 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing - PUBLIC WORKS | 3/5/2020 | | 3/9/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - Design Review | 3/5/2020 | | 3/9/2020 | | FAIL |
Katelyn Menuge
|
|
|
Upload photometric plan, locate condensers away from adjacent homes, provide downward-only lighting or indicate that uplighting will be dimmable.
|
Routing PW Drainage | 3/6/2020 | | 3/9/2020 | | PASS |
Brian Murphy
|
|
|
pad site commercial sub
|
Routing PW Street Lights | 3/6/2020 | | 3/6/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Environmental | 3/6/2020 | | 3/6/2020 | | PASS |
Zach Conde
|
|
|
|
Routing PW Sewer Design | 3/6/2020 | | 3/6/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Addressing | 3/5/2020 | | 3/6/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 3/5/2020 | | 3/6/2020 | | PASS |
Michael Zawacki
|
|
|
waiver approved, site is in commercial area with parking lot already paved and existing buildings.
|
Intake Approval | | | 3/4/2020 | | PASS |
Javier Guzman
|
|
|
Prescreen approved by JG
|
Intake Approval | | | 1/15/2020 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Provide and upload documentation (email transcripts) from Brian Murphy stating no grading and drainage plans are required. (BMURPHY@cityofboise.org)
• Provide and upload documentation (email transcripts) from Andy Long stating no ESC plans are required and the waiver letter uploaded will suffice. (AJLong@cityofboise.org)
• Per ePlan submittal standards the naming convention for drawings should be for example as follows DWG_A-0.0 Cover Sheet and what was uploaded was DWG_Loop Techonologies Office_Plans-A-0.0 Cover sheet. remove all unnecessary words within the file naming, just provide similar to your drawing index on the cover sheet DWG_(sheet ID + sheet # + discipline of sheet) see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
I have removed all unnecessary words within the file naming on this project, but I will be rejecting future project at prescreen with incorrect file naming.
• Per checklist show location of Fire Hydrants (existing and or new)
|
Application received | | | 1/10/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2020 6:25AM
|