BLD-Concrete | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PART |
Tell Riley
|
|
|
Slab on grade- Chase *screened* Phone #: ###-####//ok pend specials//
|
BLD-Other | 8/6/2020 | 8/7/2020 | 8/7/2020 | A | PART |
Tell Riley
|
|
|
screened - masonry // Chase Phone #: ###-####//masonry for gym walls//pend special inspections//
|
BLD-Foundation | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | DEFR |
Tell Riley
|
|
|
*Screened* masonary & foundation - Chase Phone #: ###-####//defer to special inspections//
|
BLD-Concrete | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PART |
Tell Riley
|
|
|
Screened- slab on grade inspection- Chase Phone #: ###-####//ok pending specials//
|
BLD-Other | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PART |
Tell Riley
|
|
|
Screened- massonary-reba inspection- Chase Phone #: ###-####//ok pending specials//
|
BLD-Footing | 7/28/2020 | 7/29/2020 | 7/29/2020 | A | PART |
Tell Riley
|
|
|
Chase *screened* Phone #: ###-####//last of the interior footers and piers--3 exterior footers//ok pending specials//
|
BLD-Concrete | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PART |
Tell Riley
|
|
|
Chase *screened* Phone #: ###-####//last of area A slab, ok pending special inspections//east part of area B slab, vapor barrier ok, no wire mesh installed yet--pend specials//
|
BLD-Footing | 7/20/2020 | 7/21/2020 | 7/21/2020 | A | PART |
Tell Riley
|
|
|
Chase Phone #: ###-####//interior footing pads in area b and c//mat footings--need to add full length verts at correct size where short verts were installed--will have checked by special inspector// all others appear ok//pending specials//
|
BLD-Concrete | 7/14/2020 | 7/14/2020 | 7/14/2020 | P | PART |
Tony Young
|
|
|
Chase *screened* Phone #: ###-####// pending special inspection
|
BLD-Foundation | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PART |
Tell Riley
|
|
|
screened // Chase Phone #: ###-####//areas b and c exterior foundation//ok pending specials//interior foundation piers and elevator pit as well//
|
BLD-Footing | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PART |
Mike Jordan
|
|
|
Screened // Chase Phone #: ###-####. Interior column pads and exterior footing in areas b and c. Ok to place pending special inspection.
|
BLD-Foundation | 6/25/2020 | 6/26/2020 | 6/26/2020 | A | PART |
Tell Riley
|
|
|
screened // Chase Phone #: ###-####//part of Area C foundation walls//ok pend specials//maintain bar clearances//
|
BLD-Footing | 6/22/2020 | 6/23/2020 | 6/23/2020 | A | PART |
Tell Riley
|
|
|
Chase *screened* Phone #: ###-####//part of area C footings//ok per plans pending all specials//
|
BLD-Footing | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PART |
Tell Riley
|
|
|
Chase Phone #: ###-####//add top mat bar in F7A footings//areas ok signed off on plans//interior footing column pads//pend all specials//
|
BLD-Foundation | 6/12/2020 | 6/12/2020 | 6/12/2020 | P | PART |
Tell Riley
|
|
|
Chase Phone #: ###-####//GYM slab//bar per plan//VB installed and taped//pend all specials//
|
BLD-Foundation | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PART |
Tell Riley
|
|
|
Chase *screened* Phone #: ###-####//portions of area B and C walls//ok when bar clearances are corrected//pend all specials//
|
BLD-Footing | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | CANC |
Tell Riley
|
|
|
Chase *screened* Phone #: ###-####//previously inspected area A footing//
|
BLD-Foundation | 6/8/2020 | 6/9/2020 | 6/9/2020 | A | PART |
Tell Riley
|
|
|
Screened-Chase Phone #: ###-####-7515//area A walls will be complete with this pour//ok pending all specials//
|
BLD-Footing | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | PART |
Tell Riley
|
|
|
screened // Chase Phone #: ###-####//area B footings-partial//ok eonding all special inspection approvals//
|
BLD-Foundation | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PART |
Tell Riley
|
|
|
screened - Chase Phone #: ###-####//continued foundation area A//appears ok//pend all specials//
|
BLD-Footing | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PART |
Tell Riley
|
|
|
screened - Chase Phone #: ###-####//contiued footings area A//appears to be ok//pend specials//
|
BLD-Foundation | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | PART |
Tell Riley
|
|
|
screened // Chase Phone #: ###-####//footing pads and large mat footing in area A//marked on plans, ok pending specials//
|
BLD-Footing | 5/26/2020 | 5/27/2020 | 5/27/2020 | A | PART |
Tell Riley
|
|
|
asked for between 9-11 if possible // Jason Phone #: ###-####//more area A footings for gym//footing sizes ok per plans//pending all special inspections//
|
BLD-Footing | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | DEFR |
Tell Riley
|
|
|
screened // Chase Phone #: ###-####//defer to specials//
|
BLD-Foundation | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Tell Riley
|
|
|
CHACE Phone #: ###-####//Area A exterior foundation wall 2" foam insulation installed//
|
BLD-Foundation | 5/14/2020 | 5/15/2020 | 5/15/2020 | A | PART |
Tell Riley
|
|
|
asking before 9am // Chase Phone #: ###-####//need to maintain clearances on bar, special inspector will be onsite and confirm//areas with electrical conduit will need permit and inspection prior to cover//special inspector onsite, pending his approvals//Area A walls and partial footing//
|
BLD-Footing | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | PART |
Mike Jordan
|
|
|
*screened* Chase, requests between 10 & noon Phone #: ###-####. Area A Footings, work in progress. Work that ws completed was ok. Ok to place concrete pending special inspection.
|
Fees Due Hold | 4/2/2020 | | 4/6/2020 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 3/31/2020 | | 4/1/2020 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 3/27/2020 | | 3/30/2020 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 3/26/2020 | | 3/26/2020 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 3/25/2020 | | 3/25/2020 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 3/24/2020 | | 3/24/2020 | | DONE |
Christina Prado
|
|
|
Check received for incorrect amount. Permit issued as courtesy
|
Issue & PRINT to be Invoiced | | | 3/23/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/23/2020 | | DONE |
|
|
|
|
Telephone call | | | 3/18/2020 | | DONE |
|
|
|
fees send to - mforrester@beniton.com, and informed that we need ACHD fees or receipt
|
OVERRIDE | | | 3/11/2020 | | |
|
|
|
|
Plan assigned to (CDM) | 2/9/2020 | 2/9/2020 | 3/11/2020 | | PASS |
Carl D Madsen
|
|
|
Elemantary School 10 day review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2020 | | DONE |
|
|
|
|
Routing PW Sewer Design | 3/11/2020 | | 3/11/2020 | | PASS |
DeAnn Brown
|
|
|
|
Permit Ready to Issue | | | 3/11/2020 | | DONE |
|
|
|
All MET
Need
GC Form
Revised Cert of Value (use state fees for plan check fee)
ACHD
|
Routing Off Site - STRUCTURAL | 2/28/2020 | | 3/11/2020 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLUMBING | 3/9/2020 | | 3/9/2020 | | PASS |
Dan Ediger
|
|
|
Per plans and the ISPC
|
Routing PW Street Lights | 3/2/2020 | | 3/2/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 2/28/2020 | | 2/28/2020 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 2/20/2020 | 2/23/2020 | 2/20/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/20/2020 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/9/2020 | | 2/20/2020 | | FAIL |
Carl D Madsen
|
|
|
KPFF
|
Routing PW Drainage | 2/10/2020 | | 2/20/2020 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 2/9/2020 | | 2/18/2020 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 2/9/2020 | | 2/14/2020 | | PASS |
Candy A. Nichols
|
|
|
CREDIT FOR DEMO
|
Routing - FIRE | 2/9/2020 | 2/9/2020 | 2/13/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 2/9/2020 | | 2/13/2020 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - ELECTRICAL | 2/9/2020 | | 2/12/2020 | | PASS |
Daryl DeGrange
|
|
|
|
Routing - PLANNING | 2/9/2020 | | 2/11/2020 | | PASS |
Karla Nelson
|
|
|
Per CUP19-00036
|
Routing - Addressing | 2/9/2020 | | 2/10/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 2/9/2020 | | 2/10/2020 | | FAIL |
Dan Ediger
|
|
|
See Changemark
|
Routing - Design Review | 2/9/2020 | | 2/10/2020 | | PASS |
Josh Wilson
|
|
|
No review required- not in Design Review Overlay
|
Routing - Erosion and Sediment | 2/9/2020 | | 2/10/2020 | | PASS |
Michael Zawacki
|
|
|
Site prep inspection required.
|
Routing PW Street Lights | 2/10/2020 | | 2/10/2020 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 2/10/2020 | | 2/10/2020 | | FAIL |
DeAnn Brown
|
|
|
Refer to changemarks on sheets C5.02 and A2.0.
|
Routing PW Solid Waste | 2/10/2020 | | 2/10/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 2/10/2020 | | 2/10/2020 | | PASS |
Rick Christenson
|
|
|
Approved with grease interceptor as shown.
|
Intake Approval | | | 2/7/2020 | | PASS |
|
|
|
|
Application received | | | 2/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 3 2020 11:52AM
|