BLD-Final | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | NR |
Mike Jordan
|
|
|
Kyle *screened* Phone #: ###-####. Exterior of building not yet compleed.
|
BLD-Final | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | NR |
Mike Jordan
|
|
|
Kyle */Screened*/ Phone #: ###-####
|
FIRE-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Kyle */Screened*/ Phone #: ###-####
|
BLD-Final | 7/31/2020 | 8/3/2020 | 8/3/2020 | P | NR |
Mike Jordan
|
|
|
screened // Kyle Phone #: ###-####. Needs fire/life/safety and zoning finals.
|
FIRE-Final Inspection | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | CANC |
Troy Cobbley
|
|
|
screened // Kyle Phone #: ###-####
|
BLD-Framing/Rough-in | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Mike Jordan
|
|
|
Screened- Kyle or Andrew Phone #: ###-####. Exterior steel stud framed walls for freezer enclosure.
|
BLD-Framing/Rough-in | 6/15/2020 | 6/16/2020 | 6/16/2020 | P | PART |
Tony Young
|
|
|
Kyle *screened* Phone #: ###-####,, interior walls ok to insulate for fire block and cover one side,, needs plumbing in one area
|
Issue PAID IN FULL permit | | | 4/30/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/30/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/23/2020 | 4/26/2020 | 4/24/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 4/23/2020 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 4/23/2020 | | DONE |
|
|
|
met: cooplivin@me.com
NEED
GC
REV VALUES
|
Plan assigned to (M_H) | 3/3/2020 | | 4/23/2020 | | DONE |
Michael Hanson
|
|
|
03/27 #520 L3 ePlan - Vanilla T.I - pending BLD20-00308
|
Routing - PLAN CHECK | 3/3/2020 | | 4/23/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - FIRE | 3/3/2020 | 3/3/2020 | 4/9/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - PLANNING | 3/3/2020 | | 3/9/2020 | | PASS |
Karla Nelson
|
|
|
Ok per CUP19-00050 must also comply with DRH19-00330
|
Routing - Design Review | 3/3/2020 | | 3/6/2020 | | FAIL |
Katelyn Menuge
|
|
|
Elevations don't match DR approval, bicycle rack requirements, new construction needs to meet 20-foot setback along Entertainment Ave.
|
Routing - Addressing | 3/3/2020 | | 3/4/2020 | | PASS |
Doug Chausow
|
|
|
New address: 1644 S Entertainment Ave
|
Routing - PUBLIC WORKS | 3/3/2020 | | 3/4/2020 | | PASS |
Candy A. Nichols
|
|
|
NO NEW PLUMBING-FEES TO BE ASSESSED WITH FUTURE TENANT
|
Routing - PLUMBING | 3/3/2020 | | 3/4/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Application received | | | 3/2/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2020 11:42AM
|
Intake Approval | | | 3/2/2020 | | PASS |
|
|
|
|