Permit Information
Permit NumberBLD20-00774
StatusIssued
Name ARMADA HOMES
Site Address 9722 W MACAW ST
Project NameEronel 3-3
Customer Number 
ePlanReviewYes
Description
***07/29 PLAN MODIFICATION TO CHANGE WINDOW U VALUES AND INSULATION VALUES AND REMOVE REBAR FROM FOUNDATION AND PATIO*** Permit for the construction of a new 1884 sq. ft., two story (first story 1201 sq. ft., second story 683 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 132 sq. ft. of covered patio/porch and a 445 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. R-1C zoning and setbacks per planning. ***RDP***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in8/3/20208/3/20208/3/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//Trimmers added under blocking used for truss hanger attachment, creating headers at 14" wide, load paths are now supported//energy ok//
BLD-Energy code compliance7/31/20207/31/20207/31/2020PPEND
DetailsBrandon Shaw
Need to provide Engineering aprroval for truss supported from blocking in garage, see correction notice...
OVERRIDE  7/30/2020  
OVERRIDE  7/30/2020  
Permit Ready to Issue  7/30/2020 DONE
plan mod approved
DO NOT REISSUE
CHANGE STATUS TO (ISS)  7/30/2020 DONE
Permit Ready to Issue  7/30/2020 DONE
**DO NOT REISSUE - PLAN MOD**
Plan assigned to (RDP)7/24/20207/24/20207/29/2020 DONE
DetailsRob Patrick
plan mod
Routing - PLAN CHECK7/27/2020 7/29/2020 PASS
DetailsRob Patrick
1 hour review fee
PLANS/APPL TAKEN TO FRONT DESK  7/29/2020 DONE
DetailsRob Patrick
Plan Modification Accepted  7/24/2020 DONE
Kelly from Armada homes called to request a plan modification. change window U values, insulation values, remove rebar from foundation and patio slabs
BLD-Framing/Rough-in7/22/20207/22/20207/22/2020PPART
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Kelly Stover//CN posted for framing corrections//2nd floor shear appears to be ok, nailing is covered//ok to insulate only--framing corrections will need to be completed//
BLD-Wall Bracing7/7/20207/8/20207/8/2020APART
DetailsBrandon Shaw
1st floor only...
BLD-Foundation5/13/20205/19/20205/19/2020PPART
DetailsTell Riley
Mark pour time at 1:30 Phone #: ###-####//WIP//
BLD-Footing5/12/20205/13/20205/13/2020PPART
DetailsTell Riley
Screened-pour time is at 2pm-Mark Phone #: ###-####//talked with Sue at zoning, verified minumum setback is 20 feet from front pin to garage//setbacks per plans, and minimum per zoning in front//need to delete rebar note from plans as general does not want it installed//
Issue PAID IN FULL permit  5/7/2020 DONE
Inspection Record Card- Bld  5/7/2020 DONE
OVERRIDE  3/16/2020  
Plan assigned to (RDP)3/4/20203/4/20203/16/2020 DONE
DetailsRob Patrick
03/17 sfd L1 ePlan
Routing - PLAN CHECK3/4/2020 3/16/2020 PASS
DetailsRob Patrick
1st review completed  3/16/2020 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  3/16/2020 DONE
DetailsRob Patrick
Permit Ready to Issue  3/16/2020 DONE
ALL MET
Route to Impact Fee Review3/4/20203/7/20203/5/2020 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL3/4/2020 3/5/2020 PASS
DetailsTroy James
Routing - PLANNING3/4/2020 3/5/2020 PASS
DetailsSue Cummings
Routing - Addressing3/4/2020 3/4/2020 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/4/2020 3/4/2020 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  3/4/2020 DONE
Intake Approval  3/4/2020 PASS
Recd Pcfee & Taken To Pln CK  3/4/2020 DONE
Application received  3/3/2020 DONE
Application submitted via PDS Online on Mar 3 2020 4:49PM