BLD-Framing/Rough-in | 8/3/2020 | 8/3/2020 | 8/3/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//Trimmers added under blocking used for truss hanger attachment, creating headers at 14" wide, load paths are now supported//energy ok//
|
BLD-Energy code compliance | 7/31/2020 | 7/31/2020 | 7/31/2020 | P | PEND |
Brandon Shaw
|
|
|
Need to provide Engineering aprroval for truss supported from blocking in garage, see correction notice...
|
OVERRIDE | | | 7/30/2020 | | |
|
|
|
|
OVERRIDE | | | 7/30/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 7/30/2020 | | DONE |
|
|
|
plan mod approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 7/30/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/30/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Plan assigned to (RDP) | 7/24/2020 | 7/24/2020 | 7/29/2020 | | DONE |
Rob Patrick
|
|
|
plan mod
|
Routing - PLAN CHECK | 7/27/2020 | | 7/29/2020 | | PASS |
Rob Patrick
|
|
|
1 hour review fee
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2020 | | DONE |
Rob Patrick
|
|
|
|
Plan Modification Accepted | | | 7/24/2020 | | DONE |
|
|
|
Kelly from Armada homes called to request a plan modification. change window U values, insulation values, remove rebar from foundation and patio slabs
|
BLD-Framing/Rough-in | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//CN posted for framing corrections//2nd floor shear appears to be ok, nailing is covered//ok to insulate only--framing corrections will need to be completed//
|
BLD-Wall Bracing | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PART |
Brandon Shaw
|
|
|
1st floor only...
|
BLD-Foundation | 5/13/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Tell Riley
|
|
|
Mark pour time at 1:30 Phone #: ###-####//WIP//
|
BLD-Footing | 5/12/2020 | 5/13/2020 | 5/13/2020 | P | PART |
Tell Riley
|
|
|
Screened-pour time is at 2pm-Mark Phone #: ###-####//talked with Sue at zoning, verified minumum setback is 20 feet from front pin to garage//setbacks per plans, and minimum per zoning in front//need to delete rebar note from plans as general does not want it installed//
|
Issue PAID IN FULL permit | | | 5/7/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/7/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/16/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 3/4/2020 | 3/4/2020 | 3/16/2020 | | DONE |
Rob Patrick
|
|
|
03/17 sfd L1 ePlan
|
Routing - PLAN CHECK | 3/4/2020 | | 3/16/2020 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 3/16/2020 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/16/2020 | | DONE |
|
|
|
ALL MET
|
Route to Impact Fee Review | 3/4/2020 | 3/7/2020 | 3/5/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 3/4/2020 | | 3/5/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/4/2020 | | 3/5/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/4/2020 | | 3/4/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/4/2020 | | 3/4/2020 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/4/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/4/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/4/2020 | | DONE |
|
|
|
|
Application received | | | 3/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 3 2020 4:49PM
|