BLD-Wall Bracing | 6/1/2020 | 6/1/2020 | 6/1/2020 | P | PASS |
Tell Riley
|
|
|
shear // Don Phone #: ###-####//nailing ok// check hold downs at framing//
|
BLD-Foundation | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PART |
Tell Riley
|
|
|
Virtual Inspection Requested // Pat Phone #: ###-####//bar drilled to exisiting//wip//
|
BLD-Footing | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PASS |
Tony Young
|
|
|
Virtual Inspection Requested // Pat Phone #: ###-####// via pictures
|
BLD-Footing | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | CANC |
Tell Riley
|
|
|
Screened- Pat Phone #: ###-####//contact left message to cancel inspection//
|
Issue PAID IN FULL permit | | | 4/10/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/10/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2020 | | DONE |
|
|
|
Emailed applicant to inform them the erosion fee was missed. That we need either the copy of the warranty deed or a letter from the current owner allowing them to pull the permit.
|
Plan assigned to (JAB) Josh | 3/25/2020 | 3/25/2020 | 4/8/2020 | | PASS |
Josh Bogle
|
|
|
03/30 addition, ePlan - 1st done
|
Routing - PLAN CHECK | 4/8/2020 | | 4/8/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 4/8/2020 | | DONE |
|
|
|
ALL MET
Need GC
Need RP
(parcel owner listed at Darwin Mouse) Parcel owner provided letter.
|
1st review completed | | | 3/31/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/25/2020 | | 3/31/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan per phone conversation with Don
|
Routing - PLANNING | 3/25/2020 | | 3/25/2020 | | PASS |
Jeff Lowe
|
|
|
|
Intake Approval | | | 3/25/2020 | | PASS |
|
|
|
|
Application received | | | 3/24/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 24 2020 12:39PM
|
Intake Approval | | | 3/24/2020 | | FAIL |
|
|
|
All drawings must my be loaded as individual sheets, and named according to ePlan Submittal Standards
|