BLD-Final | 4/17/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Brandon Shaw
|
|
|
Screened- Ryeongmin Phone #: ###-####
|
DOC - Permit Finaled | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 4/17/2020 | 4/20/2020 | 4/20/2020 | A | PASS |
Jim Page
|
|
|
Previoujsly noted items have been corrected, hood suppression system permit is complete FIR20-00281, final life fire safety inspection is complete, signatures provided on permit sign off card.
Screened- Ryeongmin Phone #: ###-####
|
Permanent Occupancy | | | 4/20/2020 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | FAIL |
Jim Page
|
|
|
Cooking appliances have been changed, added and moved under the Type 1 hood, a seperate FIR permit is required for hood fire suppression system modifications. Mount fire extinguisher as discussed and have annual inspection performed on the ABC and Class K extinguishers as discussed. Provide annual inspection on hood fire suppression system. Exit sign located in the east side of tenant space is mounted too low, exit sign must comply with 1010.1.1.1 of the 2015 IFC.
screened // ryeongmin Phone #: ###-####
|
BLD-Final | 4/16/2020 | 4/17/2020 | 4/17/2020 | P | CANC |
Brandon Shaw
|
|
|
screened // ryeongmin Phone #: ###-####
|
FIRE-Final Inspection | 4/3/2020 | 4/6/2020 | 4/6/2020 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled for a later date, point of contact informed me that the inspection request was suppose to be for AM and not PM and could not be at the tenant space for the PM time frame, this request is cancelled per conversation with point of contact.
screened // ryeongmin Phone #: ###-####
|
Permit Ready to Issue | | | 4/3/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/3/2020 | | DONE |
|
|
|
email permit and inspetion card to toakdmf60@yahoo.com
|
Print Occupancy Form | | | 4/3/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/3/2020 | | DONE |
|
|
|
when building permit is received, release Eplan
|
Meeting | | | 4/3/2020 | | DONE |
|
|
|
MIS20-00102 created for the pumbling and mechanical inpsections that need to be conducted.
|
Plan Reviewer's activity | | | 4/3/2020 | | DONE |
Javier Guzman
|
|
|
per applicants request the name got changed to Han's Chimaek
|
Case Summary (BLD) | | | 4/3/2020 | | DONE |
Javier Guzman
|
|
|
|
Print Occupancy Form | | | 4/3/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/1/2020 | 4/4/2020 | 4/2/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/25/2020 | | 4/2/2020 | | PASS |
Javier Guzman
|
|
|
|
Plan assigned to (JG) | 3/25/2020 | 3/25/2020 | 4/1/2020 | | PASS |
Javier Guzman
|
|
|
03/31 L2 KITCHENETTE LLC Occ Eval
|
Routing PW Environmental | 3/26/2020 | | 4/1/2020 | | PASS |
Zach Conde
|
|
|
Signed off in ePlan by y PW Pre-Treatment Zach Conde-PER ZACH: Spoke to the owner, and the existing grease trap will remain. Passed on ePlan with this comment: "Approved with current grease abatement." Please pass on Tidemark.
|
Case Summary (BLD) | | | 4/1/2020 | | DONE |
Javier Guzman
|
|
|
|
1st review completed | | | 4/1/2020 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/1/2020 | | DONE |
|
|
|
|
Routing - FIRE | 3/25/2020 | 3/25/2020 | 3/31/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing - Addressing | 3/25/2020 | | 3/26/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/25/2020 | | 3/26/2020 | | PASS |
Morgan Webb
|
|
|
NO ADDITIONAL CUSTOMER SERVICE AREA. NO NEW FEES
|
Intake Approval | | | 3/25/2020 | | PASS |
Javier Guzman
|
|
|
|
First Notice | | 4/30/2020 | | | |
|
|
|
|
First Notice | 4/20/2020 | 4/20/2020 | | | |
Brandon Shaw
|
|
|
|
Application received | | 3/25/2020 | | | |
|
|
|
|