Permit Information
Permit NumberBLD20-01121
StatusIssued
Name PRUETT CONSTRUCTION LLC
Site Address 5138 N BROOKFIELD PL
Project NameKopping Addition
Customer Number 
ePlanReviewYes
Description
Permit for a 1,003sq' addition that adds a Master Suite and Family room. Converting an existing Bedroom into a Powder Bath and Hallway is part of the scope. Heating/cooling of addition via mini-split - Energy Code via alt-Prescriptive. All work per plans, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Energy code compliance7/29/20207/29/20207/29/2020PPASS
DetailsTell Riley
video/photo ok if needed please call to let know // Brandon Phone #: ###-####//R21 walls and windows .31//areas under wall where no stem wall will be poured in for support//no kitchen plumbing or range outlet were present at inspection//
BLD-Energy code compliance7/27/20207/27/20207/27/2020PFAIL
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Vaughn Pruett//mechanical failed//
BLD-Framing/Rough-in7/24/20207/24/20207/24/2020PPASS
DetailsDave Hannah
Addition on right side of house, just walk around garage. Thanks. Phone #: ###-#### Inspection requested via web by Vaughn Pruett ok to insulate after mec rough in is passed
BLD-Final7/24/20207/24/20207/24/2020PCANC
DetailsDave Hannah
BLD-Framing/Rough-in7/23/20207/24/20207/24/2020ANR
DetailsTony Young
Addition on right side of house, just walk around garage. Thanks. Phone #: ###-#### Inspection requested via web by Vaughn Pruett// no mech pass yet
BLD-Framing/Rough-in7/20/20207/21/20207/21/2020ANR
DetailsTell Riley
Call first. Thanks. Phone #: ###-#### Inspection requested via web by Vaughn Pruett//called twice no answer, left message to reschedule//no one onsite//no mechanical rough in inspection has been completed//
Routing - MECHANICAL6/12/2020 6/12/2020 PASS
DetailsTroy James
New manual j report
Inspection Record Card- Bld  6/11/2020 DONE
OVERRIDE  6/10/2020  
Plan assigned to (JAB) Josh6/9/20206/9/20206/10/2020 PASS
DetailsJosh Bogle
plan mod
Routing - MECHANICAL6/9/2020 6/10/2020 PASS
DetailsTroy James
Permit Ready to Issue  6/10/2020  
plan mod
Plan Modification Accepted  6/9/2020 DONE
Plan mod requested by Vaughn Pruett
Manual J
BLD-Wall Bracing6/5/20206/8/20206/8/2020APASS
DetailsDave Hannah
Shear inspection Phone #: ###-#### Inspection requested via web by Vaughn Pruett
BLD-Foundation5/21/20205/21/20205/21/2020PPART
DetailsTell Riley
screened // Nate Phone #: ###-####//WIP//rebar installed per plans//
BLD-Footing5/12/20205/13/20205/13/2020APASS
DetailsDave Hannah
addition is outside - screened // Nate Phone #: ###-####
Telephone call  4/24/2020 DONE
sent email to vaugh informing him we still need the RP for issuance
Issue PAID IN FULL permit  4/24/2020 DONE
Inspection Record Card- Bld  4/24/2020 DONE
CHANGE ISSUED DATE  4/24/2020 DONE
Updating after accidentially reissued
Permit Ready to Issue  4/23/2020 DONE
NEED
RP
Plan assigned to (JAB) Josh4/6/20204/6/20204/22/2020 PASS
DetailsJosh Bogle
04/10 addition, ePlan - 1st done
Routing - PLAN CHECK4/22/2020 4/22/2020 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  4/22/2020 DONE
DetailsJosh Bogle
ESC yes - Energy yes
Routing - PLAN CHECK4/20/2020 4/20/2020 FAIL
DetailsJosh Bogle
calcs need stamped
1st review completed  4/13/2020 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK4/6/2020 4/13/2020 FAIL
DetailsJosh Bogle
see notes in ePlan
Routing - PLANNING4/6/2020 4/6/2020 PASS
DetailsSue Cummings
See minor redline
Intake Approval  4/6/2020 PASS
Application received  4/1/2020 DONE
Application submitted via PDS Online on Apr 1 2020 1:57PM
Intake Approval  4/1/2020 FAIL
You must first submit an application for an ADU through Planning.
Once your application has been approved, you may resubmit for a building permit.