Electrical Rough-In | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Rock A. Hudson
|
|
|
Switchgear inspection to energize. Contact Brandon Robinson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek OK to energize switch gear 2NHASWD.
|
Electrical Rough-In | 7/30/2020 | 7/30/2020 | 7/30/2020 | A | PASS |
James Ady
|
|
|
Water Heater Room Wall rough in inspection. Contact onsite electrician Cody Rhoades with any questions. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Moved wall in basement ok to cover
|
Electrical Rough-In | 7/27/2020 | 7/28/2020 | 7/28/2020 | P | PASS |
Rock A. Hudson
|
|
|
Contact Brandon for level 1 exterior soffits. Phone #: ###-#### Inspection requested via web by Tom Betty Level 1 east soffit as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | PASS |
James Ady
|
|
|
Rough in wall inspection on Level 2 North. Contact Brandon Robinson. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek electrical room, Com room and special systems room. Walls only ok to cover. (Alsom as marked on print).
|
Electrical Rough-In | 6/29/2020 | 7/1/2020 | 7/1/2020 | A | PASS |
Daryl DeGrange
|
|
|
Contact Brandon Robinson for rough in walls level 2. Phone #: ###-#### Inspection requested via web by Tom Betty Rough-in ok cover walls in pneumatic rm, generator roms as high lighted on print, signed, dated
|
Electrical Rough-In | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
James Ady
|
|
|
Contact Brandon for level 1 wall rough in. Phone #: ###-#### Inspection requested via web by Tom Betty Misc walls 1st floor as marked on contractor print ok to cover walls only
|
Electrical Rough-In | 5/4/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
James Ady
|
|
|
Contact Brandon Robinson for rooftop parapet walls. Phone #: ###-#### Inspection requested via web by Tom Betty S,E and W parapet walls only ok to cover
|
Electrical Rough-In | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PASS |
James Ady
|
|
|
Contact Brandon R. for level 1 west wall and north stairwell rough in. Phone #: ###-#### Inspection requested via web by Tom Betty N Stair well Basement walls only, West exterior wall only ok to cover
|
Electrical Rough-In | 4/6/2020 | 4/8/2020 | 4/8/2020 | A | PASS |
James Ady
|
|
|
Contact Brandon for sub-basement wall rough in from elevators to south end of basement. Phone #: ###-#### Inspection requested via web by Tom Betty Lightning protection, Basement walls, Penthouse walls ok to cover
|
Electrical Rough-In | 2/27/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
James Ady
|
|
|
Contact Brandon for west and north lightning protection ground loop system. Phone #: ###-#### Inspection requested via web by Tom Betty Remaining ground loop ok to cover
|
Electrical Rough-In | 2/27/2020 | 2/27/2020 | 2/27/2020 | P | PASS |
James Ady
|
|
|
Contact Brandon for lightning protection ground loop system. Phone #: ###-#### Inspection requested via web by Tom Betty Grounding ring as mark on contractors print only ok to cover
|
Electrical Rough-In | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PASS |
James Ady
|
|
|
Contact Brandon for underground rough in at fuel tanks on east exterior of project. Phone #: ###-#### Inspection requested via web by Tom Betty Underground around Diesel fuel tanks only. ok to cover. (Note: Diesel fuel dispensary is not considered a hazerdous area. No seal offs required other spect by engineer)
|
Electrical Rough-In | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | PASS |
James Ady
|
|
|
Underground Inspection. Please contact electrician on-site Cody Rhoades. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Basement underground Column D through G ok to cover
|
Telephone call | | | 1/9/2020 | | DONE |
|
|
|
See attached email for added value for adding HVAC controls to their project.
|
Rough-In Permanent Service | 9/18/2019 | 9/20/2019 | 9/20/2019 | A | CANC |
James Ady
|
|
|
Contact Brandon for UFER in west footing before 9:00 a.m. concrete pour. Phone #: ###-#### Inspection requested via web by Tom Betty
|
Electrical Rough-In | 9/20/2019 | 9/20/2019 | 9/20/2019 | P | PASS |
James Ady
|
|
|
Contact Brandon for UFER in west footing before 9:00 a.m. concrete pour. Phone #: ###-#### Inspection requested via web by Tom Betty UFER only ok to cover
|
Rough-In Permanent Service | 9/18/2019 | 9/19/2019 | 9/18/2019 | A | CANC |
Rock A. Hudson
|
|
|
Please inspect UFER ground on west footing before 9:00 a.m. concrete pour. Phone #: ###-#### >> Inspection requested via web by Tom Betty Inspection cancelled from web by: Tom Betty
|
Issue PAID IN FULL permit | | | 7/22/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/22/2019 | | DONE |
|
|
|
This permit was created on the web by Cathy Duchek
|