Final | 4/29/2020 | 4/29/2020 | 4/29/2020 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Card signed. Final ok
|
Final | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | FAIL |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud As per 2015 IECC C408.3.1 a lighting system commissioning report shall be completed by the registered disign professional prior to final. BCC 4-05-32, No code violation shall be retained. AC disconnecting means for tasting lounge is missing interior cover and has exposed wiring to public and is located next to a gathering shelter on east side of tasting lounge.
|
Final | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | PART |
Rock A. Hudson
|
|
|
Partial Final. Request inspection after 10AM. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Access to in duct heater not needed due to unit abandoned and access patched. Emergency egress ballast for rear patio in route to site. No card posted. TCO for kitchen and bar ok
|
Final | 3/13/2020 | 3/16/2020 | 3/16/2020 | P | FAIL |
Rock A. Hudson
|
|
|
Partial Final Phone #: ###-#### Inspection requested via web by Jeremy Cloud 110.22- Main switches powering this space shall be labelled. 300.22- Electrical penetrations shall be sealed. Cooler. 422.31- Hardwired appliances shall have disconnecting means. * Patio egress not operational.
|
Electrical Rough-In | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Adequate access shall be provided for an in duct heater in walkway ceiling above hardlid. Grid for tasting bar and panel corridor rough in ok cover
|
Electrical Rough-In | 2/17/2020 | 2/18/2020 | 2/18/2020 | P | PASS |
Rock A. Hudson
|
|
|
Kitchen ceiling Phone #: ###-#### Inspection requested via web by Jeremy Cloud Main kitchen area grid only rough in ok cover.
|
Electrical Rough-In | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Rock A. Hudson
|
|
|
walls/ceiling for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Back foyer walls complete walls and hardlid rough in ok cover
|
Electrical Rough-In | 1/9/2020 | 1/10/2020 | 1/10/2020 | A | PASS |
Rock A. Hudson
|
|
|
walls/ceilings in storefront for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel 110.26- Access shall be provided for all electrical equipment. HVAC unit buried above hardlid. 110.26(A) and (A)(4)(c)- Work space shall be provided for HVAC electrical enclosure and door of enclosure shall open to at least 90 degrees. Copper plumbing lines run in front of door blocking work space and door operation. Must be corrected for grid inspections. Tasting reception area outer walls and ceiling not ready. Back wall of tasting reception area and vestibule walls and ceiling rough in ok cover.
|
Electrical Rough-In | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Rock A. Hudson
|
|
|
Bar-Kitchen wall Phone #: ###-#### Inspection requested via web by Mike McCarrel Kitchen wall added rough in ok cover
|
Electrical Rough-In | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Rock A. Hudson
|
|
|
walls/ceilings for cover in tasting lounge Phone #: ###-#### Inspection requested via web by Mike McCarrel Areas noted rough in ok cover
|
Electrical Rough-In | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McCarrel Discussed receptacle locations in face up positions. As per 406.5(E),(F), and (H)- restrictions for counter top, work areas, and seating areas. Tasting bar soffits and duct pocket walls rough in ok cover
|
Electrical Rough-In | 10/17/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Rock A. Hudson
|
|
|
Walls for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Walls and hardlids marked on contractor print rough in ok cover
|
Electrical Rough-In | 10/2/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Daryl DeGrange
|
|
|
Walls for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Small amount of one side completed, spoke with Magnum from Kincade construction, discussed no cover without ok to cover inspection. rough-in ok cover walls marked in orange/ DKD initials on sheet AZ-1
|
Electrical Rough-In | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Rock A. Hudson
|
|
|
Underslab raceways for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Conduits noted rough in ok cover
|
Conference | 8/9/2019 | 8/12/2019 | 8/12/2019 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Mike McCarrel Discussed equipment grounding requirements on load side of transformer to 120/208 sub panel boards. As per 250.30(A)(1 thru 8) no connection is allowed to the grounded conductor and non-current carrying metal parts on load side of transformer in this case a system bonding jumper shall be installed at transformer. Equipment grounds shall be added to sub-feeds for panel boards due to non-metallic raceways present underground. Also discussed 210.8(B) GFCI requirements for other than dwelling kitchens. If a receptacles are installed for equipment in kitchen area they shall have GFCI protection, if chenged to hard wired appliances additional disconnecting means is required as per 422.31(A) and (B).
|
Issue PAID IN FULL permit | | | 7/29/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/29/2019 | | DONE |
|
|
|
This permit was created on the web by Jeremy Cloud
|
First Notice | 4/29/2020 | 4/29/2020 | | | |
Rock A. Hudson
|
|
|
|