INSP-Final Inspection | 1/19/2017 | 1/23/2017 | 1/23/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete.
|
INSP-Alarm Testing | 10/19/2015 | 10/19/2015 | 10/19/2015 | A | PART |
Thomas Walsh
|
|
|
Fire alarm interface with heat tracing panels that monitor heat trace of fire sprinkler piping exposed to cold temps. See FIR 13-00461 for details of heat trace inspection.
|
INSP-Alarm Testing | 8/12/2015 | 8/13/2015 | 8/13/2015 | A | PART |
Thomas Walsh
|
|
|
Fire alarm testing (continuation) for abaove grade SDs, FSD, HVAC shutdowns, rolldown doors (floors 4 & 5) elevator smoke guard doors,etc. Checked monitoring for alarms received - OK. Also checked exterior bell for waterflow alarms - tested OK.
|
INSP-Alarm Testing | 8/12/2015 | 8/12/2015 | 8/12/2015 | A | PART |
Thomas Walsh
|
|
|
Continuation of fire alarm system testing for JUMP Bldg, including Helix, A/G parking structure and upper structures to the 6th floor. Testing mostly of in-duct HVAC shutdown purposes. All tested OK. More testing to commence tomorrow.
|
Telephone call | | | 8/12/2015 | | DONE |
|
|
|
Charlie Bayne called regarding a smoke detector deletion in a mechanical / storage room that is exposed to the elements. The detector is not rated for the environment and the room is covered by a dry sprinkler head. I agreed with Charlie that the detector can be removed without resubmittal. This change will be required to be indicated on as built drawings.
|
INSP-Alarm Testing | 8/11/2015 | 8/11/2015 | 8/11/2015 | P | PART |
Thomas Walsh
|
|
|
Continuation of fire alarm system testing, including test of two (2) PIVs, two (2) BFP devices - both valves, and a random etst of other fire sprinkler risers and sectional control valves. All tested OK. Started FSD test of in-duct SDs to ensure shutdown of FSDs for the parking level, 1st floor kitchen and lobby and 2nd floor lobby areas. All tested OK, except for one unit in the garage that needs to be retested. More FSDs need to be tested on the upper floors including rooftop HVAV duct detectors.
|
INSP-Alarm Testing | 8/7/2015 | 8/7/2015 | 8/7/2015 | A | PART |
Thomas Walsh
|
|
|
Test of elevator recall functions for service elevator and main elevator - the third elevator not ready for testing. All elevator functions tested OK. Shunt trip power monitoring not tested this visit.
|
INSP-Alarm Testing | 7/30/2015 | 8/3/2015 | 8/3/2015 | P | CANC |
Thomas Walsh
|
|
|
No inspections called in for this permit.
|
INSP-Alarm Testing | 7/30/2015 | 8/3/2015 | 8/3/2015 | A | PART |
Thomas Walsh
|
|
|
Initial fire alarm system testing, including test of notification (speaker/strobes) throuout the JUMP bldg. including the U/G parking garage the above ground parking garage, the helix and all rooms above grade. A few devices were not very load, and the contractor agreed to modify the devices in these areas to improve audibility. Also tested fire pump functions to coincide with the fire pump commissioning test. Also tested one (1) H&D system test for the 1st floor kitchen. NOTE: Elevators, HVAC, and FSDs not ready for test yet.
|
INSP-Alarm Testing | 7/12/2015 | 7/12/2015 | 7/12/2015 | P | PART |
Thomas Walsh
|
|
|
Initial testing of fire alarm system for the Jump building, including the Helix and A/G parking structure. NOTE: U/G parking structure under permit # 13-00178. Test included functional testing for all fire sprinkler systems (wet and dry) for all levels, and stairwells, including wet pipe water flows, dry pipe trip tests, low-air alarms, waterflows, tampers, etc. All systems tested OK. Some alarm descriptions need to be revised to reflect a better location of some of the systems. Simplex to make these changes, and wil confirm at the next inspection.
|
INSP-Conference | 10/1/2014 | 10/1/2014 | 10/1/2014 | P | DONE |
Forrest France
|
|
|
Site visit completed to discuss occupant notification in the vicinity of the 1st to 4th floor NE elevator lobby and stair tower areas, ground level courtyard. Also discussed dust collection equipment, fire door, heat tracing at sprinkler mains.
|
Alarm Plan Check | 2/7/2014 | | 2/7/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/7/2014 | | DONE |
|
|
|
Plan approved with comments and drawing notation. ProjectDox updated.
|
Issue and Print Permit | | | 2/7/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/7/2014 | | 2/7/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 2/6/2014 | | DONE |
|
|
|
Resubmittal received based on 2nd review comments.
|
Alarm Plan Check | 2/4/2014 | | 2/4/2014 | | FAIL |
Lee G Meredith
|
|
|
2nd review failed. Change marks noted on drawings and review comments provided to applicant.
|
Miscellaneous action | | | 2/3/2014 | | DONE |
|
|
|
I emailed several questions to Dante regarding differences between floor plans and risers / calcs on the speaker circuits and requested more information on the deluge system that is indicated in the lobby area of floor 5. I requested information of the boundries and purpose of the system and clarification of which devices will be controlling it.
|
Miscellaneous action | | | 2/3/2014 | | DONE |
|
|
|
I received comments back from Dante that addressed most issues noted in my last email.
|
Miscellaneous action | | | 1/30/2014 | | DONE |
|
|
|
I received via email several changes that Dante indicated htat he would provide including ceiling heights in several areas and a revised floor plan for floor 6 Helix.
|
Miscellaneous action | | | 1/29/2014 | | DONE |
|
|
|
Emailed several design questions to Dante Frassa. He responded via email for each question. It was determined that the 6th floor plan that had been submitted was incorrect. Dante will resubmit the correct one once corrections have been made.
|
Plan resubmittals received | | | 1/27/2014 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 1/6/2014 | | 1/6/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/6/2014 | | FAIL |
Lee G Meredith
|
|
|
1st plan review. See review comments.
|
Miscellaneous action | | | 1/6/2014 | | DONE |
Lee G Meredith
|
|
|
emailed review comments to applicant.
|
Application received | | | 12/30/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 30 2013 11:02AM
|