Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR13-00724
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 1000 W MYRTLE ST
Project NameJUMP STRUCTURE FIRE ALARM
Customer Number 
ePlanReviewYes
Description
SimplexGrinnell will supply the equipment necessary for a design-build fire alarm system per State & Boise Fire Department requirements. The system design is based around a Simplex 41OOES network voice evacuation system with (1) Fire Alarm Control Panel (FACP) located in the Fire Command Center on 1st Floor with (1) Transponder located in the 4th Floor Helix area, both panels equipped with integrated Voice Evacuation system. A Transponder panel located on the Underground Parking Garage will be tie to the new FACP (the Underground Parking Fire Alarm System was approved under FIR13-00178).
This submittal includes manual pull station, smoke detectors above the panels and for elevator recall functions, heat detectors, duct detectors for HVAC shutdown/monitoring, in-duct detectors for f/s damper shutdown/monitoring, full notification coverage for voice evacuation, sprinkler system monitoring, fire pump monitoring, heat tape monitoring, and elevator recall/shunt trip functions.
Associated with building permit BLD13-01634.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/19/20171/23/20171/23/2017APASS
DetailsJim Page
Final fire alarm inspection passed/complete.
INSP-Alarm Testing10/19/201510/19/201510/19/2015APART
DetailsThomas Walsh
Fire alarm interface with heat tracing panels that monitor heat trace of fire sprinkler piping exposed to cold temps. See FIR 13-00461 for details of heat trace inspection.
INSP-Alarm Testing8/12/20158/13/20158/13/2015APART
DetailsThomas Walsh
Fire alarm testing (continuation) for abaove grade SDs, FSD, HVAC shutdowns, rolldown doors (floors 4 & 5) elevator smoke guard doors,etc.
Checked monitoring for alarms received - OK. Also checked exterior bell for waterflow alarms - tested OK.
INSP-Alarm Testing8/12/20158/12/20158/12/2015APART
DetailsThomas Walsh
Continuation of fire alarm system testing for JUMP Bldg, including Helix, A/G parking structure and upper structures to the 6th floor. Testing mostly of in-duct HVAC shutdown purposes. All tested OK. More testing to commence tomorrow.
Telephone call  8/12/2015 DONE
Charlie Bayne called regarding a smoke detector deletion in a mechanical / storage room that is exposed to the elements. The detector is not rated for the environment and the room is covered by a dry sprinkler head. I agreed with Charlie that the detector can be removed without resubmittal. This change will be required to be indicated on as built drawings.
INSP-Alarm Testing8/11/20158/11/20158/11/2015PPART
DetailsThomas Walsh
Continuation of fire alarm system testing, including test of two (2) PIVs, two (2) BFP devices - both valves, and a random etst of other fire sprinkler risers and sectional control valves. All tested OK.
Started FSD test of in-duct SDs to ensure shutdown of FSDs for the parking level, 1st floor kitchen and lobby and 2nd floor lobby areas. All tested OK, except for one unit in the garage that needs to be retested. More FSDs need to be tested on the upper floors including rooftop HVAV duct detectors.
INSP-Alarm Testing8/7/20158/7/20158/7/2015APART
DetailsThomas Walsh
Test of elevator recall functions for service elevator and main elevator - the third elevator not ready for testing. All elevator functions tested OK. Shunt trip power monitoring not tested this visit.
INSP-Alarm Testing7/30/20158/3/20158/3/2015PCANC
DetailsThomas Walsh
No inspections called in for this permit.
INSP-Alarm Testing7/30/20158/3/20158/3/2015APART
DetailsThomas Walsh
Initial fire alarm system testing, including test of notification (speaker/strobes) throuout the JUMP bldg. including the U/G parking garage the above ground parking garage, the helix and all rooms above grade. A few devices were not very load, and the contractor agreed to modify the devices in these areas to improve audibility.
Also tested fire pump functions to coincide with the fire pump commissioning test. Also tested one (1) H&D system test for the 1st floor kitchen.
NOTE: Elevators, HVAC, and FSDs not ready for test yet.
INSP-Alarm Testing7/12/20157/12/20157/12/2015PPART
DetailsThomas Walsh
Initial testing of fire alarm system for the Jump building, including the Helix and A/G parking structure.
NOTE: U/G parking structure under permit # 13-00178.
Test included functional testing for all fire sprinkler systems (wet and dry) for all levels, and stairwells, including wet pipe water flows, dry pipe trip tests, low-air alarms, waterflows, tampers, etc. All systems tested OK. Some alarm descriptions need to be revised to reflect a better location of some of the systems. Simplex to make these changes, and wil confirm at the next inspection.
INSP-Conference10/1/201410/1/201410/1/2014PDONE
DetailsForrest France
Site visit completed to discuss occupant notification in the vicinity of the 1st to 4th floor NE elevator lobby and stair tower areas, ground level courtyard. Also discussed dust collection equipment, fire door, heat tracing at sprinkler mains.
Alarm Plan Check2/7/2014 2/7/2014 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  2/7/2014 DONE
Plan approved with comments and drawing notation. ProjectDox updated.
Issue and Print Permit  2/7/2014 DONE
Inspection Record Card- Fire2/7/2014 2/7/2014 DONE
DetailsTisha Gallop
Plan resubmittals received  2/6/2014 DONE
Resubmittal received based on 2nd review comments.
Alarm Plan Check2/4/2014 2/4/2014 FAIL
DetailsLee G Meredith
2nd review failed. Change marks noted on drawings and review comments provided to applicant.
Miscellaneous action  2/3/2014 DONE
I emailed several questions to Dante regarding differences between floor plans and risers / calcs on the speaker circuits and requested more information on the deluge system that is indicated in the lobby area of floor 5. I requested information of the boundries and purpose of the system and clarification of which devices will be controlling it.
Miscellaneous action  2/3/2014 DONE
I received comments back from Dante that addressed most issues noted in my last email.
Miscellaneous action  1/30/2014 DONE
I received via email several changes that Dante indicated htat he would provide including ceiling heights in several areas and a revised floor plan for floor 6 Helix.
Miscellaneous action  1/29/2014 DONE
Emailed several design questions to Dante Frassa. He responded via email for each question. It was determined that the 6th floor plan that had been submitted was incorrect. Dante will resubmit the correct one once corrections have been made.
Plan resubmittals received  1/27/2014 DONE
Plan assigned to (Lee)1/6/2014 1/6/2014 DONE
DetailsLee G Meredith
1st review completed  1/6/2014 FAIL
DetailsLee G Meredith
1st plan review. See review comments.
Miscellaneous action  1/6/2014 DONE
DetailsLee G Meredith
emailed review comments to applicant.
Application received  12/30/2013 DONE
Application submitted via PDS Online on Dec 30 2013 11:02AM