INSP-Final Inspection | 12/10/2015 | 12/16/2015 | 12/16/2015 | P | PASS |
Jim Page
|
|
|
Final inspection for underground passed/complete
|
INSP-Final Inspection | 12/10/2015 | 12/11/2015 | 12/10/2015 | P | CANC |
Jim Page
|
|
|
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | PASS |
Thomas Walsh
|
|
|
Bldg L dry pipe system hydrotest (200 psi @ 2 hours) - PASSED
|
INSP-Sprinkler Rough-in | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | CANC |
Thomas Walsh
|
|
|
Wrong permit called in for this inspection. See FIR14-00751, dated 6/25 for correct permit and inspection notes.
|
INSP-Final Inspection | 5/29/2015 | 6/1/2015 | 6/1/2015 | P | CANC |
Thomas Walsh
|
|
|
Final signoff on FSUG cannot be granted until fire alarm system interface components, including tampers and waterflows, can be completed.
|
INSP-Sprinkler Rough-in/Hydro | 5/27/2015 | 5/27/2015 | 5/27/2015 | A | PASS |
Thomas Walsh
|
|
|
FSUG Hydrotest - 200 psi @ 2 hours - PASSED NOTE: Siesmic clearance around U/G stub up in riser room still needed, as noted during flush test,
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2015 | 5/27/2015 | 5/27/2015 | A | CANC |
Thomas Walsh
|
|
|
Hydrotest of FSUG supply line from city connection to BOR - 200 psi at 2hours - PASSED NOTE: Siesmic clerance still needed around stub up through concrete floor slab in riser room - noted at system flush test.
|
INSP-Supply line flush | 4/17/2015 | 4/17/2015 | 4/17/2015 | P | PART |
Katie Marron
|
|
|
Underground flush completed satisfactory. Noted that there needs to be seisimic clearance between ductile riser and floor slab in bldg L.
|
Sprinkler Plan Check | 11/25/2014 | | 11/25/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/25/2014 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Sprinkler Rough-in | 9/12/2014 | 9/15/2014 | 9/15/2014 | P | PART |
Forrest France
|
|
|
Revise thrust blocking at the 90 upstream of the ductile riser prior to cover.
|
INSP-Sprinkler Rough-in | 8/26/2014 | 8/26/2014 | 8/29/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line at building L from the meter to a point just ahead of the first 90 okayed for bury. NOTE: thrust blocking not yet installed.
|
Sprinkler Plan Check | 3/20/2014 | | 3/20/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/20/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 3/20/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 3/20/2014 | | 3/20/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 3/10/2014 | | 3/10/2014 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/19/2014 | | 2/19/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/19/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 2/12/2014 | | 2/12/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/12/2014 | | 2/12/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/12/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/12/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 1/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 28 2014 3:47PM
|