INSP-Final Inspection | 3/4/2015 | 3/5/2015 | 3/5/2015 | A | PASS |
Forrest France
|
|
|
Final inspection completed, verified finishes. Fire alarm permit finaled.
|
INSP-Final Inspection | 2/5/2015 | 2/11/2015 | 2/11/2015 | A | PART |
Forrest France
|
|
|
Functional testing completed satisfactory. Items needed prior to final include; replace damaged HD at the panel enclosure, provide knox box per plan review note #9, remove "local alarm only" signage at the manual pull stations.
|
INSP-Final Inspection | 1/22/2015 | 1/27/2015 | 1/27/2015 | A | FAIL |
Forrest France
|
|
|
Manual pull stations need relocated as indicated per the project scope and plan review comment #19, provide knox box per review note #9.
|
INSP-Final Inspection | 1/19/2015 | 1/22/2015 | 1/22/2015 | A | DEFR |
Forrest France
|
|
|
Final Inspection for Panel Change Out and Phone Line Monitoring Phone #: ###-#### Inspection requested via web by Jeremy Berg
|
Alarm Plan Check | 11/26/2014 | | 11/26/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/26/2014 | | DONE |
|
|
|
Resubmittal approved with review comments. Projectdox updated.
|
Permit Ready to Issue | | | 11/26/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/26/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/26/2014 | | 11/26/2014 | | DONE |
Kristal Soland
|
|
|
|
Plan resubmittals received | | | 11/25/2014 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 10/20/2014 | | 10/20/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 10/20/2014 | | FAIL |
|
|
|
See review comments.
|
Miscellaneous action | | | 10/20/2014 | | DONE |
|
|
|
Emailed review comments to Jason Heath .
|
Application received | | | 10/17/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2014 4:32PM
|