INSP-Final Inspection | 7/20/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Thomas Walsh
|
|
|
Trip test of the dry pipe valve, including the new accelerator - tested OK within 45 seconds. Fire sprinklers for the entire project have been tested with fire alarm interface. Inspection with final walk through needs to be conducted prior to final sign-off, including obtaining ROCs. Systems are to remain in service from this point on.
|
INSP-Final Inspection | 7/16/2015 | 7/17/2015 | 7/17/2015 | P | PART |
Thomas Walsh
|
|
|
Test/inspection of all fire sprinkler systems (dry and wet) and interface with fire alarm system, including tampers, waterflows, low-air f/ dry system, sectional control valves, and a trip test of the dry pipe valve protecting the parking garage. All devices tested OK and within time requirements, except the dry pipe valve that only delivered water within 90 seconds trip test. Therefore an accelerator device will be required on this system to get below the 60 second time requirement.
|
INSP-Sprinkler Rough-in/Hydro | 7/16/2015 | 7/16/2015 | 7/16/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrostatic pressure test of all the wet pipe systems for the above parking garage areas, including each floor of the residential building, and the clubhouse. (5 total wet systems). All tested at 200 psi @ 2hrs - All passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | CANC |
Thomas Walsh
|
|
|
Wrong permit # called in for this inspection - See permit FIR 14-00628 for inspection/test conducted this visit.
|
INSP-Sprinkler Rough-in | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | CANC |
Thomas Walsh
|
|
|
Wrong permit number requested.
|
INSP-Sprinkler Rough-in | 5/13/2015 | 5/13/2015 | 5/16/2015 | P | PASS |
Thomas Walsh
|
|
|
Clubhouse rough-in inspection. No discrepancies noted.
|
INSP-Sprinkler Rough-in | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PART |
Katie Marron
|
|
|
Tenting at 4th flr at south end completed with the exception of rm 431 (not completed) and the exterior wall in shower enclosure at rm 432. One area in room 430 adjusted on site.
|
INSP-Sprinkler Rough-in | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | PASS |
Tim Frost
|
|
|
Passed
However, I had a conference with the super. I told him there could be a potential problem with freeze ups where the insulation butts together directly above the sprinkler piping.
|
INSP-Sprinkler Rough-in | 3/26/2015 | 3/27/2015 | 3/31/2015 | P | PART |
Forrest France
|
|
|
Completed rough-in inspection for the remainder of the 4th floor living units only as noted on stamped plans. Items noted include; overspaced coverage at unit 405, missing coverage at units 430 and 432. Need to install flushing caps per plan notes.
|
INSP-Sprinkler Rough-in | 3/18/2015 | 3/19/2015 | 3/20/2015 | A | PART |
Forrest France
|
|
|
2nd floor west side living unit soffits only.
|
INSP-Sprinkler Rough-in | 3/10/2015 | 3/12/2015 | 3/12/2015 | A | PASS |
Troy Cobbley
|
|
|
Requesting RTC inspection on the 3th floor. See the city approved plans for rooms marked with "ok" and todays date where rough-in has passed.
|
INSP-Sprinkler Rough-in | 3/10/2015 | 3/11/2015 | 3/11/2015 | A | PASS |
Troy Cobbley
|
|
|
Inspection on the 4th floor was just for the general rough-in, not all drops or heads are installed. No tenting has been performed. Only apartments were looked at and not the hallway. City approved plans marked.
|
INSP-Sprinkler Rough-in | 2/26/2015 | 2/27/2015 | 3/6/2015 | A | PART |
Forrest France
|
|
|
Inspection to be on the 3rd floor. Jeremiah is your contact on site. Please call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 2/19/2015 | 2/20/2015 | 2/20/2015 | A | PART |
Forrest France
|
|
|
Partial rough-in for branchlines installed at the 3rd floor west side living units. Min. distance between heads is exceeded at five rooms -323,321,314,312,311 and 2nd floor 212. Drops are not yet installed at some locations.
|
INSP-Sprinkler Rough-in | 2/18/2015 | 2/19/2015 | 2/19/2015 | P | PART |
Forrest France
|
|
|
Rough-in inspection completed for the remainder of the 2nd floor living units. Also verified previous C/N items.
|
INSP-Sprinkler Rough-in | 2/13/2015 | 2/18/2015 | 2/18/2015 | A | PART |
Forrest France
|
|
|
Completed initial rough-in for the 2nd floor living units as annotated on approved plans. Items incude; missing sprinker at closet, overspaced coverage, sprinkler too close to ceiling fan, noted two unprotected concealed spaces, incorrect type of head at the janitors room.
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2015 | 2/17/2015 | 2/17/2015 | A | PART |
Forrest France
|
|
|
This inspection will be on the 2nd floor. Jeremiah R is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Permit Ready to Issue | | | 12/23/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/23/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/23/2014 | | 12/23/2014 | | DONE |
Kristal Soland
|
|
|
|
Sprinkler Plan Check | 12/22/2014 | | 12/22/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/22/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/13/2014 | | 12/13/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/13/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/13/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 12/12/2014 | | 12/12/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 12/12/2014 | | PASS |
|
|
|
|
Application received | | | 11/30/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 30 2014 7:31PM
|