INSP-Final Inspection | 2/27/2020 | 2/27/2020 | 2/27/2020 | A | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for underground supply complete, no pressure loss observed.
Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | CANC |
Jim Page
|
|
|
cancelled per conversation with point of contact, underground would not maintain pressure. Request will be rescheduled for a later date.
Tony Cetani is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 2/19/2020 | 2/19/2020 | 2/19/2020 | A | DONE |
Jim Page
|
|
|
Underground main line flush is complete.
|
INSP-Sprinkler Rough-in | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for IBR and FDC piping complete, IBR and FDC piping under footing complete, approved for cover. Remaining underground supply piping to be installed at a later date.
Good morning! This is for an UG RTC today. Thank you for all of your help! Bryan is the contact for this. Have a great day! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Application received | | | 2/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 25 2019 1:59PM
|
Intake Approval | | | 2/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/25/2019 | | 2/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/25/2019 | | 2/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/25/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/25/2019 | | DONE |
|
|
|
|