INSP-Final Inspection | 3/6/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Robert Chambers is the contact. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauges.
Robert Chambers is the contact. Thanks! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2020 | 3/10/2020 | 3/10/2020 | A | CANC |
Jim Page
|
|
|
Rescheduled for PM, this request is cancelled.
Robert Chambers is the contact. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover approved for overhead fire sprinkler piping.
Robert Chambers is the field contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 10/9/2019 | 10/10/2019 | 10/10/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, levels 1 and 2 are approved for cover, tenting to be installed at a later date on level 3, cover for level 3 is not approved until tenting inspection is performed. Hydrostatic test was not performed due to temperature, until permenant heat is established and 40 degrees is maintained per NFPA 13 an official hydro will not be completed.
Robert Chambers is the contact for this RTC /Hydro inspection. We appreciate your help. Thank you! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan assigned to (Stumbaugh) | 10/2/2019 | | 10/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Sprinkler Plan Check | 10/8/2019 | | 10/8/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $113.50 (1hr ($65) + 10 heads($48.50))
|
Permit Ready to Issue | | | 10/8/2019 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 10/8/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/2/2019 | | DONE |
|
|
|
Per email from Cam, request to open permit for a plan modification
|
Issue and Print Permit | | | 7/29/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/26/2019 | | 7/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/26/2019 | | 7/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 7/26/2019 | | DONE |
|
|
|
met
|
Application received | | | 7/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 25 2019 5:47PM
|