INSP-Final Inspection | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Tanner *screened* Phone #: ###-####
|
INSP-Supply line flush | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush was witnessed. Tanner Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2020 | 1/23/2020 | 1/23/2020 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro supply line witnessed on building B. underground // Bill Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2020 | 1/16/2020 | 1/16/2020 | P | FAIL |
Troy Cobbley
|
|
|
Underground supply line hydro failed due to visible loss of pressure on the guage.
bld B // Kyle Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok for cover. KYLE Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/8/2020 | 1/8/2020 | 1/8/2020 | P | FAIL |
Jim Page
|
|
|
Provide protective coding on all thread rod being used on the restraint at the IBR or remove all thread rod, IBR has thrust block installed. Cover is not approved.
Kyle Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping OK for cover.
Chris - underground inspection Phone #: ###-####
|
Issue and Print Permit | | | 10/18/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/17/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/17/2019 | | 10/17/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 10/17/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/17/2019 | | 10/17/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 10/17/2019 | | DONE |
|
|
|
|
Application received | | | 10/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 16 2019 3:16PM
|