INSP-Final Inspection | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, final fire sprinkler inspection is complete.
Call James before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | FAIL |
Jim Page
|
|
|
Fire sprinkler head is closer than 36 inches to ceiling fan, minimum 36 inches required away from ceiling fan.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/14/2020 | 7/14/2020 | 7/14/2020 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, could not final due too fire alarm inspection not being scheduled, inspection request will be rescheduled too conicide with fire alarm inspection.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/9/2020 | 7/10/2020 | 7/10/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need one of the sidewalls modified for height and interconnection with the FACP tested.
Call Anthony before heading out, backflow test scheduled to be completed before noon. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final. I noted that the water was not turned on yet, pendants too close and I need verification that the sidewall sprinkler heads can be installed where they have been installed as far as distance from ceiling. Also need city approved plans and small documents.
Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush witnessed.
Coordinated for 9:30am with Jim Page and Pat with SUEZ. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 1/7/2020 | 1/8/2020 | 1/8/2020 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, rough to cover inspection for overhead fire sprinkler piping complete, all tenting in place at time of inspection. Cover is approved, sticker provided for cover. Piping before backflow, per plumbing code and SUEZ requirements piping must be suitable for potable water, black iron pipe is not suitable for potable water, black iron pipe before the backflow will need to be replaced, will verify piping change during next inspection.
As built approved. Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Sprinkler Plan Check | 1/6/2020 | | 1/7/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
No new devices
|
Permit Ready to Issue | | | 1/7/2020 | | DONE |
|
|
|
as builts met
|
Issue and Print Permit | | | 1/7/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 12/31/2019 | | 1/6/2020 | | DONE |
Mark Stumbaugh
|
|
|
as builts
|
INSP-Sprinkler Rough-in | 12/30/2019 | 12/31/2019 | 12/31/2019 | A | FAIL |
Jim Page
|
|
|
Notated areas where piping install does not match city approved drawings. Notated city approved drawings where sidewalls were installed instead of pendant heads, sidewall are a different K factor. 20X20 spacing needs to be verified, no notes on plan allowing 20X20 spacing. 1 1/4 pipe supplying riser is not shown on the drawings.
Overhead rough and tenting, call James before heading out. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan resubmittals received | | | 12/31/2019 | | DONE |
|
|
|
per nate, requested as builts
|
INSP-Sprinkler Rough-in | 11/13/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/12/2019 | 11/13/2019 | 11/13/2019 | P | PART |
Jim Page
|
|
|
Hydrostatic for underground supply witnessed, no pressure loss observed, water will be drained from stub in to building.
Underground Rough and Hydro, call James when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 11/12/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 11/6/2019 | | DONE |
|
|
|
permit was not paid for yet and wanted to make changes to plans. removed approved plans from eplan
|
Plan assigned to (Stumbaugh) | 11/6/2019 | | 11/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 11/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 11/6/2019 | | 11/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1hr
no new devices
|
Permit Ready to Issue | | | 11/6/2019 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 10/22/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/22/2019 | | 10/22/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 10/22/2019 | | |
|
|
|
|
Intake Approval | | | 10/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/18/2019 | | 10/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 10/18/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/18/2019 | | 10/18/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 10/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2019 3:31PM
|