INSP-Sprinkler Rough-in | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was for the underground supply piping. The piping intself is ok but it can not be coverfed until a solution is proposed for the lack of minimum cover over this piping. I spoke to St. Lukes Construction, Rocky, and he will be speaking to their engineers for a solution. Yes we do need this underground cover inspection. Justin is the Foreman. Thanks Brad Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 7/7/2020 | 7/7/2020 | 7/7/2020 | P | CANC |
Troy Cobbley
|
|
|
THIS IS AN UNDERGROUND COVER INSPECTION. JUSTIN IS OUR CONTACT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | PART |
Jim Page
|
|
|
Areas inspected for rough in inspection are marked with pink highlighter on city approved drawings for levels 2 and 3. Cover inspection will be required after flex heads are installed in grid.
screened // John Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 6/8/2020 | 6/9/2020 | 6/9/2020 | A | PART |
Jim Page
|
|
|
Areas inspected for rough in inspection are marked with green highlighter on city approved drawings. Cover inspection will be required after flex heads are installed in grid.
creened // John Phone #: ###-####
|
INSP-Sprinkler Rough-in | 4/10/2020 | 4/14/2020 | 4/14/2020 | P | PART |
Jim Page
|
|
|
Notated city approved drawings with red ink for preset hangers to be covered.
THIS IS FOR THE MECH. ROOM ON 1ST FLOOR. JUSTIN NELSON IS OUR ON SITE FOREMAN. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
Sprinkler Plan Check | 2/28/2020 | | 3/2/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/2/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/2/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/2/2020 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/2/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/28/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/21/2020 | | 2/26/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 2/21/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 11/20/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 11/6/2019 | | 11/14/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 11/14/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 11/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2019 10:37AM
|
Intake Approval | | | 11/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 11/6/2019 | | 11/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|