INSP-Final Inspection | 7/29/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Brian Carlisle
|
INSP-Final Inspection | 7/29/2020 | 7/30/2020 | 7/29/2020 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Carlisle Inspection cancelled from web by: Brian Carlisle
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro test was witnessed with no pressure loss.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Supply line flush | 3/20/2020 | 3/24/2020 | 3/24/2020 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush witnessed.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground tie-in piping is ok for cover.
hone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground cover approved except the tie in which is not complete yet.. Phone #: ###-#### Inspection requested via web by Sam Ball
|
Application received | | | 12/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 2 2019 11:38AM
|
Intake Approval | | | 12/2/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/2/2019 | | 12/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 12/2/2019 | | 12/2/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 12/2/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/2/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 12/2/2019 | | DONE |
|
|
|
|