INSP-Final Inspection | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Greg Ruxton
|
|
|
Notification appliances, voice annunciation system, initiating devices and air handler shutdown passed testing and inspection.
Buck Tom Phone #: ###-#### Inspection requested via web by Ken Webster
|
INSP-Final Inspection | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | PART |
Jim Page
|
|
|
Fire sprinkler monitoring for furnituremove in complete, remaining items to be inspected at a later date.
Buck Tom Phone #: ###-#### Inspection requested via web by Ken Webster
|
INSP-Conference | 3/9/2020 | 3/11/2020 | 3/11/2020 | A | DONE |
Jim Page
|
|
|
Fire conference complete.
Inspection requested via web by Ken Webster
|
Issue and Print Permit | | | 2/28/2020 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/28/2020 | | DONE |
|
|
|
|
1st review completed | | | 2/27/2020 | | FAIL |
|
|
|
Comments on FA.0.0 have not been addressed.
|
Plan resubmittals received | | | 2/27/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 2/27/2020 | | 2/27/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/27/2020 | | DONE |
|
|
|
Resubmittal passed.
Permit fees are to be double the normal amount as the contractor has begun work without having a permit.
|
Permit Ready to Issue | | | 2/27/2020 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 2/26/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/31/2020 | | PASS |
|
|
|
|
1st review completed | | | 1/31/2020 | | FAIL |
|
|
|
Visible notification is inadequate in corridors and possibly in the attic. Smoke detection appears to be inadequate in the attic.
|
Plan assigned to (Lee) | 1/29/2020 | | 1/29/2020 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 1/29/2020 | | DONE |
|
|
|
Emailed design questions to Ken regarding attic visible notification and detection.
|
Application received | | | 1/28/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 28 2020 3:17PM
|