INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Cover sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PART |
Jim Page
|
|
|
Missing head has been installed, rough in inspection is complete, no tenting installed at time of inspection, cover is not approved..
Verify missing head in hallway has been installed. Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 3/19/2020 | 3/20/2020 | 3/20/2020 | P | FAIL |
Jim Page
|
|
|
City approved drawings has been notated with red ink where a sprinkler head was not installed. No tenting install at time of inspection.
Johnathon Phone #: ###-####
|
Permit Ready to Issue | | | 3/19/2020 | | DONE |
|
|
|
**plan mod - do not reissue**
|
CHANGE STATUS TO (ISS) | | | 3/19/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 3/17/2020 | | 3/18/2020 | | DONE |
Mark Stumbaugh
|
|
|
as builts
|
Sprinkler Plan Check | 3/18/2020 | | 3/18/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 3/18/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/18/2020 | | 3/18/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1 hr
No new devices
|
Plan resubmittals received | | | 3/17/2020 | | DONE |
|
|
|
Tom with JBL fire protection opening for as builts
|
Issue and Print Permit | | | 2/18/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/13/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/13/2020 | | 2/13/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/13/2020 | | DONE |
|
|
|
met
|
Intake Approval | | | 2/11/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/11/2020 | | 2/11/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/11/2020 | | 2/11/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/11/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/10/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 10 2020 5:34PM
|