INSP-Final Inspection | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete. Irrigation shutdown during flow switch activation observed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Fees Due Hold | 4/7/2020 | | 4/7/2020 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PASS |
Jim Page
|
|
|
Tenting has been corrected, all tenting in place at time of inspection, cover is approved. Cover sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/5/2020 | 4/6/2020 | 4/6/2020 | A | FAIL |
Jim Page
|
|
|
Tenting not installed correctly in numerous areas, pocket between sheetrock and piping will be compromised, cover is not approved. Second failure for same item, a re-inspection fee has been attached.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/3/2020 | 4/3/2020 | P | FAIL |
Jim Page
|
|
|
Tenting not installed correctly in numerous areas, pocket between sheetrock and piping will be compromised, cover is not approved..
Tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | FAIL |
Jim Page
|
|
|
Tenting not installed at time of inspection, cover is not approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection is complete, no tenting installed at time of inspection, cover is not approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Issue and Print Permit | | | 2/25/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/18/2020 | | 2/19/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/19/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/19/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/18/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/18/2020 | | 2/18/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/13/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 13 2020 6:04PM
|