Permit Information
Permit NumberFIR20-00148
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 302 W IDAHO ST
Project NameLe Soleil Daycare
Customer Number 
ePlanReviewYes
Description
Full automatic wet sprinkler system in 1 floor light hazard occupancy. Upright sprinkler protection throughout to protect obstructed combustible construction. Underground connection from city water Main alleyway.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/8/20206/9/20206/9/2020PPASS
DetailsJim Page
Final fire sprinkler inspection is complete.

Contact: Jeremiah Robison Phone #: ###-#### Inspection requested via web by Hunter Fillmore
INSP-Final Inspection6/5/20206/8/20206/8/2020PCANC
DetailsTroy Cobbley
To be rescheduled per Jeremiah.

Looking to final after hydro at some point in the day. Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in/Hydro6/5/20206/8/20206/8/2020APASS
DetailsTroy Cobbley
Over head Hydro witnessed with no pressure loss and the remote FDC piping has been coated and wrapped. It is ok to bury.

Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in/Hydro6/3/20206/4/20206/4/2020PPASS
DetailsJim Page
Rough to cover inspection complete, all areas approved for cover. No hydro performed.

Mike Martin is contact. Hydro and rough-in on overhead thank you. Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in/Hydro6/4/20206/4/20206/4/2020PDONE
DetailsJim Page
Underground and remote FDC hydro witnessed, no pressure loss observed at underground supply gauge.
INSP-Supply line flush6/4/20206/4/20206/4/2020PCANC
DetailsJim Page
Request was for underground hydro, not flush, this request is cancelled.

underground hydro Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in/Hydro6/3/20206/3/20206/3/2020PCANC
DetailsJim Page
Cancelled per conversation with point of contact due too pressure loss, hydro will be rescheduled for a later date.

Mike Martin is contact-Underground Hydro Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Supply line flush6/3/20206/3/20206/3/2020PDONE
DetailsJim Page
Underground main line flush witnessed.

Mike Martin is contact Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in5/27/20205/28/20205/28/2020PPASS
DetailsJim Page
Rough to cover inspection for undergorund supply complete, approved for cover.

Approval to cover on underground.
Contact: Mike Martin Phone #: ###-#### Inspection requested via web by Hunter Fillmore
Sprinkler Plan Check5/26/2020 5/27/2020 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  5/27/2020 DONE
DetailsMark Stumbaugh
Review time 3hrs
No new devices
Permit Ready to Issue  5/27/2020 DONE
Plan mod #2 approved- Do Not issue
CHANGE STATUS TO (ISS)  5/27/2020 DONE
Plan Modification Accepted  5/19/2020  
DetailsGemma Flores
plan mod
Plan assigned to (Stumbaugh)5/19/2020 5/19/2020 DONE
DetailsMark Stumbaugh
plan mod
CHANGE STATUS TO (ISS)  5/18/2020 DONE
Sprinkler Plan Check4/10/2020 4/17/2020 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  4/17/2020 DONE
DetailsMark Stumbaugh
Review Time 3hrs
No new devices
Permit Ready to Issue  4/17/2020 DONE
**PLAN MOD - DO NOT REISSUE**
Plan assigned to (Stumbaugh)4/10/2020 4/10/2020 DONE
DetailsMark Stumbaugh
plan mod
Plan Modification Accepted  4/10/2020 DONE
Hunter requested the workflow to be opened for a plan mod.
Plan resubmittals received  3/10/2020 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check3/10/2020 3/10/2020 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  3/10/2020 DONE
DetailsMark Stumbaugh
Permit Ready to Issue  3/10/2020 DONE
met
Issue and Print Permit  3/10/2020 DONE
Intake Approval  3/9/2020 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)3/9/2020 3/9/2020 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check3/9/2020 3/9/2020 FAIL
DetailsMark Stumbaugh
1st review completed  3/9/2020 FAIL
DetailsMark Stumbaugh
Application received  2/28/2020 DONE
Application submitted via PDS Online on Feb 28 2020 9:51AM