Fees Due Hold | 4/9/2020 | | 6/12/2020 | | DONE |
Christina Prado
|
|
|
|
INSP-Final Inspection | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | PART |
Jim Page
|
|
|
Final fire alarm inspection for TCO phase 1 level 1 is complete.
|
INSP-Final Inspection | 5/13/2020 | 5/13/2020 | 5/13/2020 | P | PART |
Jim Page
|
|
|
Final fire alarm inspection for TCO phase 1 level 2 complete.
|
Plan assigned to (Lee) | 3/9/2020 | | 3/9/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 3/9/2020 | | FAIL |
|
|
|
No product data provided. Returned to Paul so it can be uploaded.
|
1st review completed | | | 3/9/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 3/9/2020 | | 3/9/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/9/2020 | | DONE |
|
|
|
Passed, as noted on design drawings.
|
Permit Ready to Issue | | | 3/9/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/9/2020 | | DONE |
|
|
|
|
Application received | | | 3/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2020 3:40PM
|