Permit NumberFIR20-00190
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1030 W RIVER ST
Project NameBiomark Chamber TI
Customer Number 
ePlanReviewYes
Description
(BIOMARK) Fire Sprinkler Permit to attach to existing main and run a line to the relocated test chamber. The chamber will have 6 heads protecting the inside.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/7/20204/8/20204/8/2020APASS
DetailsJim Page
Plans have been submitted, install matches city approved drawings, final inspection is complete.

Kenny Caldwell is the contact. Thanks for all your help! Phone #: ###-#### Inspection requested via web by Stan Beus
CHANGE STATUS TO (ISS)  4/6/2020 DONE
Plan assigned to (Stumbaugh)4/2/2020 4/3/2020 DONE
DetailsMark Stumbaugh
as built
Sprinkler Plan Check4/3/2020 4/3/2020 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  4/3/2020 DONE
DetailsMark Stumbaugh
Review Time 1 hr
No new devices
Permit Ready to Issue  4/3/2020 DONE
**AS BUILT - DO NOT REISSUE**
INSP-Final Inspection4/1/20204/2/20204/2/2020PPART
DetailsJim Page
Final fire sprinkler inspection for scope of work is complete, install is per NFPA13, pipe sizing is different than what was submitted, need to verify pipe sizing will work or corrections will be required.

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/1/20204/2/20204/2/2020PPASS
DetailsJim Page
Rough in inspection for scope of work is complete, will need to verify pipe size changes will work for application, pipe sizing is different than what was submitted.

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
Plan resubmittals received  4/2/2020 DONE
Kyle requested an as built work flow to be opened.
INSP-Sprinkler Rough-in4/1/20204/1/20204/1/2020PCANC
DetailsJim Page
Cancelled per conversation with point of contact, will be rescheduled for a later date.

Kenny Caldwell is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection3/31/20204/1/20204/1/2020PCANC
DetailsJim Page
Cancelled per conversation with point of contact, will be rescheduled for a later date.

Kenny Caldwell is the contact. Thanks (: Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in3/31/20204/1/20204/1/2020PCANC
DetailsJim Page
Kenny Caldwell is the contact. Thanks(: Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
Issue and Print Permit  3/18/2020 DONE
Intake Approval  3/17/2020 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)3/17/2020 3/17/2020 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check3/17/2020 3/17/2020 PASS
DetailsMark Stumbaugh
1st review completed  3/17/2020 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  3/17/2020 DONE
Permit Ready to Issue  3/17/2020 DONE
met
Application received  3/16/2020 DONE