INSP-Final Inspection | 8/4/2020 | 8/5/2020 | 8/5/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Contact Hayden Randolph ###-#### 30 min prior to Fire Final Insp start please, he is requesting a 1 PM inspection time if at all possible.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2020 | 8/3/2020 | 8/3/2020 | P | PASS |
Troy Cobbley
|
|
|
Overhead huydro witnessed with no pressure loss.
Contact Hayden Randolph ###-#### 30 min prior to Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
CHANGE STATUS TO (ISS) | | | 7/29/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/27/2020 | | 7/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review time 3 hrs
7 new devices
|
Permit Ready to Issue | | | 7/28/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Plan assigned to (Stumbaugh) | 7/24/2020 | | 7/27/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
INSP-Sprinkler Rough-in | 7/23/2020 | 7/24/2020 | 7/24/2020 | A | PASS |
Troy Cobbley
|
|
|
All remaining piping can be covered. Plan mods are required showing the changes. Contact Scott Carter ###-#### 30 min prior to RTC Insp. start please
Thank YOU
Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
Plan Modification Accepted | | | 7/24/2020 | | DONE |
|
|
|
Requested by Terri
|
INSP-Sprinkler Rough-in | 7/22/2020 | 7/28/2020 | 7/23/2020 | P | CANC |
Troy Cobbley
|
|
|
Contact Scott Carter III ###-#### 30 min prior to RTC insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/13/2020 | 7/14/2020 | 7/14/2020 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" with todays date where piping is ok to cover.
Contact Scott Carter ###-#### 30 min prior to Part RTC insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
(F) Reprint permit | | | 6/11/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/9/2020 | | DONE |
|
|
|
|
Intake Approval | | | 6/8/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/8/2020 | | 6/8/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/8/2020 | | 6/8/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 6/8/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/8/2020 | | DONE |
|
|
|
|
Application received | | | 5/20/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2020 2:19PM
|