Permit Ready to Issue | | | 7/29/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Issue and Print Permit | | | 7/29/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/28/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Instead of updated files being uploaded.
Files with different file names are repeatingly being uploaded.
Updated files that version original files need to be uploaded.
|
Plan resubmittals received | | | 7/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/28/2020 | | 7/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2020 | | DONE |
Mark Stumbaugh
|
|
|
review time 4 hrs total
no new devices
|
Plan resubmittals received | | | 7/27/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 7/24/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/24/2020 | | 7/24/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/22/2020 | | 7/23/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod to show flex whips
|
Sprinkler Plan Check | 7/23/2020 | | 7/23/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 7/22/2020 | | DONE |
|
|
|
plan mod
|
INSP-Sprinkler Rough-in | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | FAIL |
Jim Page
|
|
|
Plans will need to be re-submitted to show use of flex drops in the grid ceiling. Add head where duct work is blocking coverage on first floor, notated on city approved drawing. Add sway brace that was not installed on level 2. Space under first floor stairs appears to be a combustible concealed pocket, if area is combustible then heads will have to be added or filled with non-combustilble insulation as discussed. Add upright head under duct work as notated on city approved drawings.
Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia McLain
|
INSP-Sprinkler Rough-in | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | PASS |
Troy Cobbley
|
|
|
1st floor piping above the hardlids, as marked on the plans, is ok for cover.
Please call Chris Ford rough-in on the 1st floor please Phone #: ###-#### Inspection requested via web by Jessia McLain
|
Issue and Print Permit | | | 6/15/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/12/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/12/2020 | | 6/12/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/12/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/10/2020 | | 6/11/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 6/10/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/4/2020 | | 6/9/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 6/4/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 5/27/2020 | | 6/3/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 6/3/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 5/27/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 5/27/2020 | | 5/27/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 5/26/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Need more detailed description of work.
Checklist needs to be filled out completely.
|
Application received | | | 5/21/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2020 3:12PM
|