INSP-Sprinkler Rough-in/Hydro | 7/14/2020 | 7/14/2020 | 7/14/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed, no pressure loss observed at riser provided gauge.
Call James before heading out, rough/hydro/tenting. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/14/2020 | 7/14/2020 | 7/14/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, cover is approved. All tenting in place at time of inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/13/2020 | 7/13/2020 | 7/13/2020 | A | FAIL |
Jim Page
|
|
|
Contractor was to meet at 0845 per text conversation, waited until 9AM for contractor. System was not pumped up at time of inspection, due to water on floor it appears a repair was made. Section of tenting missing by attic access, cover is not approved, proceeded to next inspection.
As built approved. Call James before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | A | PART |
Jim Page
|
|
|
Previously noted items have been corrected, install matches what is submitted, head has been added under stairs at top of closet.
|
Permit Ready to Issue | | | 7/10/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT REISSUE**
|
CHANGE STATUS TO (ISS) | | | 7/10/2020 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 7/9/2020 | 7/9/2020 | 7/9/2020 | A | FAIL |
Troy Cobbley
|
|
|
Inspection turned into a walk-through/conference. I noted that the plans do need to be resubmitted for changes and a head needs to be added at the top fo the under/stairs to meet NFPA 13D 8.2.7. No piping to be covered yet. Could not do hydro since a head needs to be added.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan assigned to (Stumbaugh) | 7/9/2020 | | 7/9/2020 | | DONE |
Mark Stumbaugh
|
|
|
as builts
|
Plan resubmittals received | | | 7/9/2020 | | DONE |
|
|
|
As built work flow requested to be open.
|
Sprinkler Plan Check | 7/9/2020 | | 7/9/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2020 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod
Review time 1hr
1 new device
|
Issue and Print Permit | | | 6/12/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/5/2020 | | 6/10/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/10/2020 | | DONE |
|
|
|
MET
|
Plan resubmittals received | | | 6/5/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 6/4/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/2/2020 | | 6/4/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 6/2/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/2/2020 | | 6/2/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 5/29/2020 | | DONE |
|
|
|
Application submitted via PDS Online on May 29 2020 11:41AM
|