INSP-Sprinkler Rough-in | 8/11/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover.
Underground rough to cover at Suez connection point. Call Anthony before you head out. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 7/14/2020 | 7/14/2020 | 7/14/2020 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover. The last stick of pipe from the 45 elbow to Suez valve still needs inspected when installed for cover. Underground partial rough to cover, no hydro (not connected to city water yet, to be hydro''d once connection is finished). Call Anthony when heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Permit Ready to Issue | | | 7/13/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/13/2020 | | DONE |
|
|
|
|
Intake Approval | | | 7/10/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/10/2020 | | 7/10/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/10/2020 | | 7/10/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 7/10/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 7/2/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Waiting for BLD to be issued
|
Application received | | | 7/1/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 1 2020 3:44PM
|