INSP-Sprinkler Rough-in | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. I noted and spoke to the fitter that if the back room is used for storage then the pendant heads are overspaced.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
Intake Approval | | | 7/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/16/2020 | | 7/16/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/16/2020 | | 7/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 7/16/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 7/16/2020 | | DONE |
|
|
|
MET
|
Issue and Print Permit | | | 7/16/2020 | | DONE |
|
|
|
|
Application received | | | 7/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 15 2020 3:16PM
|