INSP-Final Inspection | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Jim Page
|
|
|
Fire beel has been repaired, final fire sprinkler inspection is complete.
|
INSP-Final Inspection | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | FAIL |
Jim Page
|
|
|
Circuit breaker for bell is on, bell did not function on flow switch activation.
Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/13/2020 | 8/13/2020 | 8/13/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection. Rough in inspection is complete, cover has been approved.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2020 | 8/11/2020 | 8/11/2020 | A | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed at city pressure, no pressure loss observed at riser provided gauge.
|
INSP-Sprinkler Rough-in | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PART |
Jim Page
|
|
|
Rough in inspection is complete, tenting not installed at time of inspection.
Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Intake Approval | | | 7/31/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/31/2020 | | 7/31/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/31/2020 | | 7/31/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 7/31/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 7/31/2020 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/31/2020 | | DONE |
|
|
|
|
Application received | | | 7/30/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 30 2020 8:22PM
|