Change Expiration Date Only | | | 4/22/2020 | | DONE |
Jason Blais
|
|
|
A 180 day extension is approved. This is the first extension for an issued permit.
|
Telephone call | | | 4/21/2020 | | DONE |
|
|
|
request for extension- email forward to Jason see DOC_Email
|
Routing - FIRE | 3/24/2020 | 3/24/2020 | 4/13/2020 | | PASS |
Erika Akin
|
|
|
|
Permit Ready to Issue | | | 4/13/2020 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 4/13/2020 | | DONE |
|
|
|
|
Routing - FRONT DESK | 3/24/2020 | | 4/13/2020 | | PASS |
Judith Amador
|
|
|
plan mod- changes to landscape and minor grade changes around retaining wall JCA
|
Plan assigned to (JCA) Judith | 3/24/2020 | 3/24/2020 | 4/10/2020 | | DONE |
Judith Amador
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2020 | | DONE |
|
|
|
plan mod approved
|
Routing PW Environmental | 3/24/2020 | | 4/10/2020 | | PASS |
Zach Conde
|
|
|
PLAN MOD-PER ZACH: Grading only. BLD plans have GT. Passed on ePlan. Please pass on Tidemark.
|
Routing PW Drainage | 4/9/2020 | | 4/9/2020 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLANNING | 3/24/2020 | | 4/6/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - Erosion and Sediment | 3/24/2020 | | 4/3/2020 | | PASS |
Andy J. Long
|
|
|
|
Routing - PLUMBING | 3/24/2020 | | 4/3/2020 | | PASS |
Daryl Spivey
|
|
|
plan mod
|
GRD-Conference | 3/31/2020 | 4/2/2020 | 4/2/2020 | A | DONE |
Mike Jordan
|
|
|
requesting speacial inspection and Mike Jordan // didn''t leave name Phone #: ###-####
|
GRD-Other | 3/24/2020 | 3/27/2020 | 3/27/2020 | A | PART |
Mike Jordan
|
|
|
rebar // angela Phone #: ###-####. Work in progress on rebar install. Ok to place concrete pending special inspection approval.
|
GRD-Other | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | CANC |
Mike Jordan
|
|
|
rebar for retaining wall // angela Phone #: ###-####. rescheduled for tomorrow in the am.
|
GRD-Other | 3/23/2020 | 3/26/2020 | 3/26/2020 | A | CANC |
Mike Jordan
|
|
|
rebar // Angela Phone #: ###-####
|
Routing PW Drainage | 3/24/2020 | | 3/26/2020 | | FAIL |
Jason C. Taylor
|
|
|
PLAN MOD -See changemarks in eplan. JCT
|
Routing PW Street Lights | 3/24/2020 | | 3/25/2020 | | PASS |
Tom Marshall
|
|
|
PLAN MOD
|
Routing PW Sewer Design | 3/24/2020 | | 3/25/2020 | | PASS |
DeAnn Brown
|
|
|
PLAN MOD. Coordinate any sewer modifications with West Boise Sewer District.
|
Routing PW Solid Waste | 3/24/2020 | | 3/24/2020 | | PASS |
Evan Carpenter
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 3/24/2020 | | DONE |
|
|
|
Plan Modification to bulb outs near trash enclosure. Does not affect valuation. See application in Docs
|
Routing - PUBLIC WORKS | 3/24/2020 | | 3/24/2020 | | CA |
Candy A. Nichols
|
|
|
plan mod
|
Plan assigned to (JCA) Judith | 2/4/2020 | 2/4/2020 | 2/4/2020 | | DONE |
Judith Amador
|
|
|
|
Routing - FRONT DESK | 2/4/2020 | | 2/4/2020 | | PASS |
Judith Amador
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/4/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/4/2020 | | DONE |
|
|
|
plan mod #2 approved
|
CHANGE STATUS TO (ISS) | | | 2/4/2020 | | DONE |
|
|
|
plan mod #2 approved
|
Routing PW Drainage | 1/30/2020 | | 2/4/2020 | | PASS |
Brian McGowan
|
|
|
Plan mod- Percolation test were completed in the field at the depth of the proposed seepage bed and results provided a higher infiltratin rate (3.8"/hr). The seepage beds were redisigned to the latest infiltration rate and updated on the Grading Plan and Drainage Plan.
|
Routing - PUBLIC WORKS | 1/30/2020 | | 1/31/2020 | | PASS |
Morgan Webb
|
|
|
Plan mod -Percolation test were completed in the field at the depth of the proposed seepage bed and results provided a higher infiltratin rate (3.8"/hr). The seepage beds were redisigned to the latest infiltration rate and updated on the Grading Plan and Drainage Plan.
|
Plan Modification Accepted | | | 1/30/2020 | | DONE |
|
|
|
Percolation test were completed in the field at the depth of the proposed seepage bed and results provided a higher infiltratin rate (3.8"/hr). The seepage beds were redisigned to the latest infiltration rate and updated on the Grading Plan and Drainage Plan.
|
Permit Ready to Issue | | | 1/23/2020 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/23/2020 | | DONE |
|
|
|
plan mod
|
Routing PW Street Lights | 1/21/2020 | | 1/22/2020 | | PASS |
Tom Marshall
|
|
|
PLAN MOD
|
Routing PW Solid Waste | 1/21/2020 | | 1/22/2020 | | PASS |
Evan Carpenter
|
|
|
PLAN MOD
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2020 | | DONE |
|
|
|
plan mod
|
Routing PW Sewer Design | 1/21/2020 | | 1/21/2020 | | PASS |
DeAnn Brown
|
|
|
Building is connecting to wet-line sewer in West Boise Sewer District. Coordinate sewer design with West Boise Sewer District.
|
Routing - PLANNING | 1/21/2020 | | 1/21/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 1/21/2020 | | 1/21/2020 | | PASS |
Candy A. Nichols
|
|
|
plan mod
|
Routing PW Drainage | 1/21/2020 | | 1/21/2020 | | PASS |
Brian Murphy
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 1/17/2020 | | DONE |
|
|
|
Landscaping reduced from 3.5' to 3' between south building face and sidewalk. Retaining wall modified to be combination of the previously proposed sheet pile wile and cast in place wall section. Traffic rated concret parapet replace with pedestrian railing on top of wall and traffic rated barrier behind the wall . South wing of retaining was realigned along sidewalk. Storm drain catch basin near wall relocated and storm drain line invert elevations adjusted.
|
Telephone call | | | 12/23/2019 | | DONE |
|
|
|
emailed Matt asking him to return the signed permit to me
|
Issue PAID IN FULL permit | | | 12/19/2019 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 12/19/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/13/2019 | | |
|
|
|
emailed Matt Kalbus at matt.kalbus@brandthg.com to let him know that we received the fees, but still need and RP before we can issue the permit.
|
Plan assigned to (JCA) Judith | 11/25/2019 | 11/25/2019 | 12/2/2019 | | DONE |
Judith Amador
|
|
|
|
Routing - PLAN CHECK | 12/2/2019 | | 12/2/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FRONT DESK | 12/2/2019 | | 12/2/2019 | | PASS |
Tisha Gallop
|
|
|
Structural sheet wall reviewed by CDM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/2/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/2/2019 | | DONE |
|
|
|
emailed permit to matt.kalbus@brandthg.com
met: Need: RP
met: Adjusted Cert of Value
|
Plan assigned to (JCA) Judith | 10/30/2019 | 10/30/2019 | 11/22/2019 | | DONE |
Judith Amador
|
|
|
|
Routing PW Drainage | 10/31/2019 | | 11/22/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - FRONT DESK | 11/22/2019 | | 11/22/2019 | | PASS |
Judith Amador
|
|
|
|
1st review completed | | | 11/22/2019 | | DONE |
|
|
|
|
Routing PW Solid Waste | 11/15/2019 | | 11/18/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - FRONT DESK | 10/30/2019 | | 11/7/2019 | | FAIL |
Judith Amador
|
|
|
fail per PW Solid waste
|
Routing - FIRE | 10/31/2019 | 10/31/2019 | 11/6/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLANNING | 10/31/2019 | | 11/5/2019 | | PASS |
Josh Wilson
|
|
|
DRH19-00248
|
Routing PW Environmental | 10/31/2019 | | 11/5/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 10/31/2019 | | 11/1/2019 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure as currently depicted is inaccessible for collection due to excessive backing required of collection vehicle after servicing. Collection trucks will not back up over 70 feet due to safety concerns. The distance from the enclosure to the nearest turnaround point is approximately 100 feet.
|
CHANGE STATUS TO (REV) | | | 11/1/2019 | | DONE |
|
|
|
|
Routing - PLUMBING | 10/31/2019 | | 10/31/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing PW Street Lights | 10/31/2019 | | 10/31/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 10/31/2019 | | 10/31/2019 | | PASS |
DeAnn Brown
|
|
|
Building connecting to wet-line sewer in West Boise Sewer District.
|
Routing - PUBLIC WORKS | 10/31/2019 | | 10/31/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - Erosion and Sediment | 10/31/2019 | | 10/31/2019 | | PASS |
Andy J. Long
|
|
|
Site preparation inspection with Boise ESC division is required prior to earthwork and BMP installation per approved ESC plan/SWPPP. Need to list Boise certified ESC Responsible Person.
|
Routing PW Sewer Design | 10/30/2019 | | 10/30/2019 | | FAIL |
DeAnn Brown
|
|
|
Building is located in West Boise Sewer District. Note to coordinate sewer connection with West Boise Sewer District on the utility plan.
|
Intake Approval | | | 10/30/2019 | | FAIL |
|
|
|
The following drawing plans need to be re-uploaded- C1.10_DEMOLITION, C2.10 EROSION CONTROL PLAN, C3.10 SITE PLAN, C4.10 GRADING PLAN, C4.20 DRAINAGE PLAN,C5.10 UTILITY PLAN
|
Routing - Addressing | 10/30/2019 | | 10/30/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/30/2019 | | 10/30/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/30/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/30/2019 | | DONE |
|
|
|
paid ESC intake fees
|
Intake Approval | | | 10/30/2019 | | PASS |
|
|
|
|
Application received | | | 10/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2019 8:46AM
|
Application received | | 10/31/2019 | | | CANC |
|
|
|
|