INSP-Final | 5/13/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Katie Marron
|
|
|
Scope of work completed satisfactory. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 4/30/2015 | 5/1/2015 | 5/1/2015 | P | PART |
Katie Marron
|
|
|
Hydrostatic test completed satisfactory. Completed rough-in inspection. Verified seismic bracing, retaining straps and riser/aux drain complete.
|
INSP-Supply line flush | 4/16/2015 | 4/20/2015 | 4/20/2015 | P | PART |
Katie Marron
|
|
|
Underground supply flush completed satisfactory.
|
INSP-Supply line flush | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | FAIL |
Katie Marron
|
|
|
Insufficient means provided to complete flushing.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2015 | 4/8/2015 | 4/9/2015 | P | NR |
Forrest France
|
|
|
Missing siesmic bracing, retaining straps, tie-ins. Riser and aux. drain incomplete at this time. Partial inspection only. Per Forrest France.
|
INSP-Supply line flush | 4/7/2015 | 4/8/2015 | 4/9/2015 | P | FAIL |
Forrest France
|
|
|
Provide sufficient method to complete flushing per NFPA 13. Inspection completed per Forrest France
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2015 | 1/28/2015 | 1/28/2015 | A | PART |
Forrest France
|
|
|
UG fire supply line okayed for cover per inspection completed by T. Cobbley 1/27 at the initial visit for the hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2015 | 1/27/2015 | 1/27/2015 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed.
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2015 | 1/26/2015 | 1/26/2015 | P | CANC |
Forrest France
|
|
|
Call prior to going Phone #: 2087619666 >> Inspection requested via mobile web by Ron Larson Inspection cancelled via mobile web on Monday, January 26, 2015.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/15/2015 | | 1/15/2015 | | PASS |
Tim Frost
|
|
|
|
Issue and Courier | | | 1/15/2015 | | DONE |
Candy A. Nichols
|
|
|
emailed Shelley at NACFR
|
Plan resubmittals received | | | 1/13/2015 | | DONE |
Candy A. Nichols
|
|
|
resubmittals received-4 each Larson fire protection, NACFR permit app, owners info,app # 603, hydraulic calcs,FP-1, FP-2, took to Lee M
|
Plan assigned to (Tim) | 1/7/2015 | | 1/7/2015 | | DONE |
Tim Frost
|
|
|
|
1st review completed | | | 1/7/2015 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 1/7/2015 | | 1/7/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/7/2015 | | DONE |
|
|
|
Emailed contractor and Shelly review
|
Issue and Courier | | | 1/7/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 1/5/2015 | | |
|
|
|
|