INSP-Final | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 4/23/2015 | 4/27/2015 | 4/27/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide knox box, provide signage on riser room door and provide map at the facp
|
INSP-Alarm Testing | 4/21/2015 | 4/21/2015 | 4/21/2015 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. I spoke to Nathan about rescheduling
|
CHANGE STATUS TO (ISS) | | | 4/21/2015 | | DONE |
|
|
|
was finaled by mistake-still needs the fire alarm final
|
INSP-Final | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PASS |
Katie Marron
|
|
|
Scope of work completed. Rough in and final inspections passed. Fire Sprinkler permit finaled.
|
INSP-Alarm Testing | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | CANC |
Katie Marron
|
|
|
Permit number and inspection type does not match scope of work.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/18/2015 | | 3/18/2015 | | PASS |
Tim Frost
|
|
|
|
Issue and Courier | | | 3/18/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/11/2015 | | DONE |
Candy A. Nichols
|
|
|
resubmittals recieved 3 sets of each sheet-HZ-001, HZ-002, HZ-101, HZ-301, HZ-302, HZ-303, HZ-501 & HZ-701-took to Tim Frost
|
1st review completed | | | 3/4/2015 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 3/4/2015 | | 3/4/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/4/2015 | | DONE |
|
|
|
Email contractor and Shelly review.
|
Application received | | | 2/25/2015 | | |
|
|
|
|
Plan assigned to (Tim) | 2/25/2015 | | | | |
Tim Frost
|
|
|
|