Permit Information
Permit NumberBLD18-04520
StatusIssued
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 982 N MAPLE GROVE RD
Project NameRosewood Apartments Bldg 11
Customer NumberBLD18-04521
ePlanReviewYes
Description
**2 BUILDING PERMITS IN EPLAN UNDER BLD18-04520** (ROSEWOOD APARTMENTS) (BUILDING #11) //08/01/19 PLAN MOD TO UTILITY LINE LOCATIONS AND LANDSCAPE PLANS. JAR// // 07/09/19 PLAN MOD TO CONSTRUCT A 2-HOUR FIRE WALL FOR BUILDING AREA FOR TYPE VB CONSTRUCTION. Permit for the construction of a new 47,415 sq ft, 3-story, 36-unit apartment building (identified as Type VII on plans). Work to include general site work including the demolition of existing residential structures and the construction of the new building per the approved plans. Alternate to use the 2018 IBC 704.4.1 for Type VA construction of interior columns. Special inspections required per attached Form 310. Carports to be constructed under separate building permit. All buildings are to be fully fire sprinklered with an NFPA 13-R system as required for residential occupancy and story increase. Exterior decks and breezeways to be protected. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/13/20208/13/20208/13/2020APASS
DetailsGreg Ruxton
Passed Fire Life Safety.

Fire/Life Safety Inspection for Occupancy. Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Framing/Rough-in4/10/20204/13/20204/13/2020APASS
DetailsMike Jordan
Ceiling drops framing inspection for cover, Building 11 - Tower 3 (12 units). Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Wall cover4/3/20204/3/20204/3/2020PPASS
DetailsMike Jordan
Cover inspection for ceiling drops framing in Building 11 - Tower 2 (12 Units). Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Energy code compliance3/25/20203/26/20203/26/2020APASS
DetailsMike Jordan
Insulation and RC inspection for cover in Building 11 -Tower 3 (North 12 units) Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Framing/Rough-in3/18/20203/19/20203/19/2020APASS
DetailsMike Jordan
Energy Seal, Fire Caulking ; Framing for cover at Building 11 - Tower 3. (North 12 units). Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Framing/Rough-in3/18/20203/18/20203/18/2020PFAIL
DetailsMike Jordan
Energy Seal, Fire Caulking ; Framing for Cover of Building 11 - Tower 3 (North 12 units). Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Ceiling Grid Inspection3/16/20203/16/20203/16/2020PPASS
DetailsDave Hannah
tower 1 // Chris Phone #: ###-#### fur downs ok to cover
BLD-Energy code compliance3/6/20203/6/20203/6/2020PPASS
DetailsMike Jordan
chris Phone #: ###-####. Gyp added behind ADA tub and blocking added.
BLD-Framing/Rough-in2/28/20202/28/20202/28/2020PPASS
DetailsTell Riley
tower 2 // Chris Phone #: ###-#### Inspection requested via web by Brittany Hill//fire caulk added as we walked through//need gyp board behind ada shower//add blocking for ada bathroom units 105 and 106//ok to insulate//
BLD-Energy code compliance2/23/20202/24/20202/24/2020APASS
DetailsMike Jordan
RC channel and insulation inspection for cover in Tower 1. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Framing/Rough-in2/19/20202/19/20202/19/2020APASS
DetailsMike Jordan
Energy Seal, Fire Caulking ; Framing Building 11 - Tower 1. Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Framing/Rough-in2/18/20202/18/20202/18/2020PNR
DetailsMike Jordan
Building 11 tower 1 Framing, Fire Caulking, Energy Seal. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Framing/Rough-in2/17/20202/18/20202/18/2020ANR
DetailsMike Jordan
Building 11 tower 1 Framing, Fire Caulking, Energy Seal. Phone #: ###-#### Inspection requested via web by Kris Linnell. moved to pm.
BLD-Framing/Rough-in1/15/20201/15/20201/15/2020PPASS
DetailsMike Jordan
South East End Walls framing for cover for plumbing fur out wall. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Framing/Rough-in12/31/20191/2/20201/2/2020APASS
DetailsMike Jordan
Framing inspection at tubs ; showers for insulation and pre-rock. Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Wall cover12/30/201912/30/201912/30/2019PPASS
DetailsMike Jordan
Building 11, Gridline 7, 2-hr wall second layer joint overlaps Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Energy code compliance12/27/201912/27/201912/27/2019PPART
DetailsBrandon Shaw
Gridline 7, 2-hr wall insulation
OK to cover...
BLD-Framing/Rough-in12/26/201912/26/201912/26/2019PPART
DetailsTony Young
Framing inspection of Gridline 7 for 2hr Firewall, prior to insulation. Phone #: ###-#### Inspection requested via web by Bob Goodwin// ok to cover
BLD-Conference12/10/201912/12/201912/12/2019ADONE
DetailsMike Jordan
Fire Caulking and Fire Proofing Conference with GC and Sub-contractors at
9:00 A.M. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Framing/Rough-in12/2/201912/3/201912/3/2019APASS
DetailsMike Jordan
Full exterior shear inspection for weather barrier cover. Phone #: ###-#### Inspection requested via web by Kris Linnell. 1st. 2nd. and 3rd. floor exterior shear and exterior floor to floor straps. interior holdowns and anchor bolts as well ok. Still need interior floor to floor straps.
BLD-Framing/Rough-in11/25/201911/26/201911/26/2019PPASS
DetailsMike Jordan
Shear inspection only in breezeways for Pre-Rock Cover. Phone #: ###-#### Inspection requested via web by Kris Linnell. 1st, 2nd, and 3rd floor breezeways only ok.
BLD-Concrete10/3/201910/4/201910/4/2019PPASS
DetailsMike Jordan
North Half of Building 11 Slab and interior thicken footings reinforcement Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Concrete9/20/20199/23/20199/23/2019PPASS
DetailsMike Jordan
South Half of Building 11 Building slab. Phone #: ###-#### Inspection requested via web by Kris Linnell. Interior thickend footings and column pad footings ok.
BLD-Energy code compliance9/6/20199/9/20199/9/2019APASS
DetailsMike Jordan
North Half of building 11 stem wall insulation. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Energy code compliance9/5/20199/6/20199/6/2019PCANC
DetailsMike Jordan
Stem wall insulation on North Half of building 11. Phone #: ###-#### >> Inspection requested via web by Kris Linnell Inspection cancelled from web by: Kris Linnell
BLD-Energy code compliance8/16/20198/19/20198/19/2019APASS
DetailsMike Jordan
South Half of building 11 energy code compliance for stem wall insulation. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Footing8/16/20198/19/20198/19/2019APASS
DetailsMike Jordan
North Half Building 11 footing rebar inspection. Concrete scheduled for 11:45 A.M.- Third Party inspector scheduled onsite for pour. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Foundation8/9/20198/12/20198/12/2019PDEFR
DetailsMike Jordan
Building 11- South Half Stem Walls Inspection requested via web by Kris Linnell. Ok to place concrete pending speciial inspection..
BLD-Footing7/31/20198/1/20198/1/2019PPART
DetailsMike Jordan
gridline 1 through gridline 5 // Bob Phone #: ###-####. exterior and breezeway footings, south half, work in progress. Ok to place concrete pending special inspection.