BLD-Aging Inspection | 6/26/2020 | 6/26/2020 | 6/30/2020 | | PEND |
Tell Riley
|
|
|
|
BLD-Conference | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | DONE |
Tell Riley
|
|
|
conference with contractor, mechanical contractor and inspectors, was scheduled under wrong permit//will need to have calcs and engineers approval and or fix for RTU units that have changed location and size, drawings including mechanical will need to be submitted for plan modification//
|
BLD-Framing/Rough-in | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PART |
Tell Riley
|
|
|
call ahead // Kent Phone #: ###-####//insulation installed in existing walls that were open //backing added for accesibility requirements//ok to cover vertical wall ONLY//still need mechanical and fire sprinkler sign offs prior to covering any ceilings//no access to fire riser room--also will need inspected for rated walls and penetrations//
|
BLD-Framing/Rough-in | 2/3/2020 | 2/4/2020 | 2/4/2020 | P | FAIL |
Tell Riley
|
|
|
call ahead // Ken Phone #: ###-####//need fire sprinkler roug in completed//add backing for Accessibility//secure demising wall studs//provide wall assembly for 1 hr room at fire riser//
|
BLD-Framing/Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PART |
Tell Riley
|
|
|
Ken- please call for access Phone #: ###-####//issues with addresses and permits for this building//told Ken he needs to go downtown and fix address issues//need mechanical permit//ok to insulate exterior walls and one side demising wall//
|
BLD-Framing/Rough-in | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | CANC |
Tell Riley
|
|
|
metal stem wall // Kent Phone #: ###-####/ Ken had questions on demising wall--plans show to underside of roof sheathing--wall stops at roof insulation--refered him to architect//some walls have been one sided--asked him to leave uncovered until all trades passed and framing is approved//
|
BLD-Framing/Rough-in | 11/21/2019 | 11/21/2019 | 11/21/2019 | P | PART |
Tell Riley
|
|
|
Call ahead 30 minutes - truss bracing // Kent Phone #: ###-####truss bracing // Kent Phone #: ###-####//engineering and engineers letter from site visit and approval onsite dated Nov 20, 2019 stamped and signed reviewed onsite//trusses ok per engineer//
|
BLD-Wall Bracing | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | CANC |
Tell Riley
|
|
|
call for keycode access // Kim Phone #: ###-####//CN posted still needs completed//updated engineering needed to reflect what was performed onsite that does not reflect the approved truss fixes//no wall bracing inspection needed at this time//
|
BLD-Framing/Rough-in | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | FAIL |
Tell Riley
|
|
|
ken Phone #: ###-####//CN posted//truss fixes do not all reflect engineered fixes//see CN onsite//
|