Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD19-00526
StatusUnder Review
Name ESI
Site Address 11910 W FAIRVIEW AVE
Project NameVillage East - Building A
Customer NumberBLD19-00526-00536, 538-539
ePlanReviewYes
Description
(13 PERMITS IN EPLAN UNDER BLD19-00526) (VILLAGE EAST – BUILDING A – RESIDENTIAL APARTMENT BUILDING) (PUD18-00042) (DRH18-00528) (4-29-20 PLAN MODIFICATION TO UPDATE THE PLUMBING DRAWINGS TO MATCH MODIFICATIONS IN THE FIELD.) (4-16-20 PLAN MODIFICATION TO CHANGE THE POTABLE WATER PLUMBING SYSTEM FOR ALL APARTMENT UNITS. PEX MANABLOCK MANIFOLDS WILL NOT BE USED.) The NFPA 13-R fire sprinkler system is used for occupancy. To construct a 35,650 square foot, 3 story apartment building (11,950 square foot 1st story, 11,850 square foot 2nd story, and 11,850 square foot 3rd story) with a total of 36 dwelling units (12 on each story). All dwelling units on the 1st story are required to comply as Type B dwelling units (11 Type B and one Type A). Since there is no elevator in this building, the dwelling units located on the 2nd and 3rd stories are not regulated for accessibility to the disabled. Work is to include concrete footings, concrete stem walls between conditioned and unconditioned spaces, concrete pedestals, concrete slab on grade with thickened slab at interior bearing walls and R-10 perimeter slab edge insulation between conditioned and unconditioned spaces, 2x6 walls between conditioned and unconditioned spaces with R-20 cavity insulation, wood columns, shear walls with gypsum panels or structural wood panels and hold downs, an unconditioned fire-resistance-rated corridor on each story, two unconditioned 1-hr fire-resistance-rated exterior stairways, 1-hr dwelling unit separation walls between dwelling units, draftstops in the attic, 1-hr dwelling unit separation floors between dwelling units, engineered wood truss roof system with a structural wood panel roof deck and R-49 insulation installed on top of the ceiling with the attic vented to the outside, roof overbuilds, ladder and roof hatch to access roof top heat pumps, exterior windows, interior doors between conditioned and unconditioned spaces, exterior cementitious lap siding, exterior brick veneer, exterior stucco, guards, handrails, asphalt shingles, 3-ply roofing membrane at flat roof areas, roof drains and overflow drains, interior millwork, and interior finishes. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The design for the engineered wood trusses is a deferred submittal item. The fire sprinkler system is required to comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall cover7/1/20207/2/20207/2/2020APART
DetailsTell Riley
Drop ceiling cover inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//drops on first floor ok when fire caulk added where discussed//
BLD-Wall cover6/23/20206/24/20206/24/2020APART
DetailsTell Riley
2nd floor drop ceiling inspection for cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//fur downs ok//fire caulk added while onsite//shear walls--a couple units need edges blocked and nails added--Jon will send pictures of corrections//
BLD-Wall Bracing6/10/20206/11/20206/11/2020PPART
DetailsTell Riley
Gyp shear inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//screws need to meet 4" oc per plans in units-301,304,305 and 312//third floor inspection only//
BLD-Wall cover6/9/20206/10/20206/10/2020PPART
DetailsTell Riley
3rd floor drop ceiling inspection for cover and gyp shear walls Phone #: ###-#### Inspection requested via web by Travis Blackburn//firecaulk areas noted//move attic access and add gyp//
BLD-Wall Bracing6/8/20206/8/20206/8/2020PPASS
DetailsTell Riley
Additional hardware and hold downs added after the fact Phone #: ###-#### Inspection requested via web by Travis Blackburn//added hold downs and floor to floor strapping--ok//
BLD-Framing/Rough-in6/5/20206/5/20206/5/2020PPART
DetailsTell Riley
Riser room approval for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//plans show 2x4 framing with R21 insulation--need architect to clarify//
BLD-Energy code compliance5/21/20205/21/20205/21/2020PPART
DetailsTell Riley
1st floor energy inspection for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok, do not cover area where main fire sprinkler lines are cut through joist, waiting for joist repair/approval before cover//
BLD-Framing/Rough-in5/19/20205/19/20205/19/2020PPART
DetailsTell Riley
1st floor reinspect Phone #: ###-#### Inspection requested via web by Travis Blackburn//corretions made from yesterday//still need joist approval for drilled joists for fire sprinkler mains//
BLD-Framing/Rough-in5/18/20205/18/20205/18/2020PNR
DetailsTell Riley
1st floor inspection to allow insulation Phone #: ###-#### Inspection requested via web by Travis Blackburn//too many corrections, will call back in//
BLD-Energy code compliance5/18/20205/18/20205/18/2020PPART
DetailsTell Riley
2nd floor insulation inspection for cover approval Phone #: ###-#### Inspection requested via web by Travis Blackburn//2nd floor energy ok, add in one location as discussed//
BLD-Framing/Rough-in5/12/20205/13/20205/13/2020PPART
DetailsTell Riley
Review framing on corridors at all floors Phone #: ###-#### Inspection requested via web by Travis Blackburn//minor framing corrections and fire caulking needed//jeremy will take photos, all areas are marked on walls in red//
BLD-Framing/Rough-in5/12/20205/12/20205/12/2020PPART
DetailsTell Riley
2nd floor only inspection for approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//firecaulk areas noted//provide RFI for joist spacing over 16" oc//
BLD-Energy code compliance5/11/20205/11/20205/11/2020PPART
DetailsTell Riley
3rd floor only of A Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok when VB is fixed//
BLD-Framing/Rough-in5/6/20205/6/20205/6/2020PPART
DetailsTell Riley
3rd floor only for approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate, trades ok, minor framing corrections we will check at energy//
BLD-Framing/Rough-in5/1/20205/4/20205/4/2020APART
DetailsTell Riley
Inspect trusses and hardware at 3rd floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//east half of building//trusses located in wrong areas in corridor need addressed//OG girder hangers and ply connections need addressed//some bracing on trusses, need to add hardware at corridor truss blocking//will need to verify corrections//
BLD-Framing/Rough-in4/30/20205/1/20205/1/2020APART
DetailsTell Riley
Inspect truss bracing and hardware on 3rd floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//truss bracing and layout, see layout sheet for minor corrections, need details on truss clips at walls, ad hardware at blocking along corridors//west half of building was looked at//will need to verify corrections//
BLD-Framing/Rough-in3/18/20203/19/20203/19/2020ADONE
DetailsTell Riley
Inspection for prerock areas behind tubs only. Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Wall Bracing1/27/20201/28/20201/28/2020PPASS
DetailsMike Jordan
Exterior hardware inspection to include floor to floor straps and H2.5''s that will cover with soffit on balconies and breezeways Phone #: ###-#### Inspection requested via web by Travis Blackburn. floor to floor straps istalled. H2.5 installed at 3rd floor balcony areas.
BLD-Wall Bracing1/27/20201/27/20201/27/2020PPART
DetailsTell Riley
Shear inspection of exterior panels on bldg A. Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add nails in areas discussed at area 4//need to add hot dip galvanized nails at PT//
BLD-Concrete12/6/201912/9/201912/9/2019APART
DetailsTell Riley
We are pouring the patio slabs for building A and K at 10 AM on Monday. Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//WIP//
BLD-Concrete10/23/201910/24/201910/24/2019APASS
DetailsTell Riley
Special Inspection on site for reinforcement and concrete testing. Concrete scheduled for 6:30am. I will also take pictures for your reference and see what we can see when you arrive. Phone #: ###-#### Inspection requested via web by Travis Blackburn//pass pending specials//
BLD-Foundation10/3/201910/3/201910/3/2019PPASS
DetailsTell Riley
Pouring stem walls at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//
BLD-Footing9/30/20199/30/20199/30/2019PPASS
DetailsTell Riley
2nd half of building footings//bar ok--ok to pour pending specials inspections//
BLD-Footing9/24/20199/25/20199/25/2019PPART
DetailsTell Riley
Concrete is scheduled for 2pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//only half of the footing is complete//ok per plans//pending specials//