BLD-Wall cover | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PART |
Tell Riley
|
|
|
Drop ceiling cover inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//drops on first floor ok when fire caulk added where discussed//
|
BLD-Wall cover | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PART |
Tell Riley
|
|
|
2nd floor drop ceiling inspection for cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//fur downs ok//fire caulk added while onsite//shear walls--a couple units need edges blocked and nails added--Jon will send pictures of corrections//
|
BLD-Wall Bracing | 6/10/2020 | 6/11/2020 | 6/11/2020 | P | PART |
Tell Riley
|
|
|
Gyp shear inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//screws need to meet 4" oc per plans in units-301,304,305 and 312//third floor inspection only//
|
BLD-Wall cover | 6/9/2020 | 6/10/2020 | 6/10/2020 | P | PART |
Tell Riley
|
|
|
3rd floor drop ceiling inspection for cover and gyp shear walls Phone #: ###-#### Inspection requested via web by Travis Blackburn//firecaulk areas noted//move attic access and add gyp//
|
BLD-Wall Bracing | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Tell Riley
|
|
|
Additional hardware and hold downs added after the fact Phone #: ###-#### Inspection requested via web by Travis Blackburn//added hold downs and floor to floor strapping--ok//
|
BLD-Framing/Rough-in | 6/5/2020 | 6/5/2020 | 6/5/2020 | P | PART |
Tell Riley
|
|
|
Riser room approval for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//plans show 2x4 framing with R21 insulation--need architect to clarify//
|
BLD-Energy code compliance | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | PART |
Tell Riley
|
|
|
1st floor energy inspection for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok, do not cover area where main fire sprinkler lines are cut through joist, waiting for joist repair/approval before cover//
|
BLD-Framing/Rough-in | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Tell Riley
|
|
|
1st floor reinspect Phone #: ###-#### Inspection requested via web by Travis Blackburn//corretions made from yesterday//still need joist approval for drilled joists for fire sprinkler mains//
|
BLD-Framing/Rough-in | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | NR |
Tell Riley
|
|
|
1st floor inspection to allow insulation Phone #: ###-#### Inspection requested via web by Travis Blackburn//too many corrections, will call back in//
|
BLD-Energy code compliance | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PART |
Tell Riley
|
|
|
2nd floor insulation inspection for cover approval Phone #: ###-#### Inspection requested via web by Travis Blackburn//2nd floor energy ok, add in one location as discussed//
|
BLD-Framing/Rough-in | 5/12/2020 | 5/13/2020 | 5/13/2020 | P | PART |
Tell Riley
|
|
|
Review framing on corridors at all floors Phone #: ###-#### Inspection requested via web by Travis Blackburn//minor framing corrections and fire caulking needed//jeremy will take photos, all areas are marked on walls in red//
|
BLD-Framing/Rough-in | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | PART |
Tell Riley
|
|
|
2nd floor only inspection for approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//firecaulk areas noted//provide RFI for joist spacing over 16" oc//
|
BLD-Energy code compliance | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PART |
Tell Riley
|
|
|
3rd floor only of A Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok when VB is fixed//
|
BLD-Framing/Rough-in | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PART |
Tell Riley
|
|
|
3rd floor only for approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate, trades ok, minor framing corrections we will check at energy//
|
BLD-Framing/Rough-in | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PART |
Tell Riley
|
|
|
Inspect trusses and hardware at 3rd floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//east half of building//trusses located in wrong areas in corridor need addressed//OG girder hangers and ply connections need addressed//some bracing on trusses, need to add hardware at corridor truss blocking//will need to verify corrections//
|
BLD-Framing/Rough-in | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | PART |
Tell Riley
|
|
|
Inspect truss bracing and hardware on 3rd floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//truss bracing and layout, see layout sheet for minor corrections, need details on truss clips at walls, ad hardware at blocking along corridors//west half of building was looked at//will need to verify corrections//
|
BLD-Framing/Rough-in | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | DONE |
Tell Riley
|
|
|
Inspection for prerock areas behind tubs only. Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Wall Bracing | 1/27/2020 | 1/28/2020 | 1/28/2020 | P | PASS |
Mike Jordan
|
|
|
Exterior hardware inspection to include floor to floor straps and H2.5''s that will cover with soffit on balconies and breezeways Phone #: ###-#### Inspection requested via web by Travis Blackburn. floor to floor straps istalled. H2.5 installed at 3rd floor balcony areas.
|
BLD-Wall Bracing | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PART |
Tell Riley
|
|
|
Shear inspection of exterior panels on bldg A. Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add nails in areas discussed at area 4//need to add hot dip galvanized nails at PT//
|
BLD-Concrete | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PART |
Tell Riley
|
|
|
We are pouring the patio slabs for building A and K at 10 AM on Monday. Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//WIP//
|
BLD-Concrete | 10/23/2019 | 10/24/2019 | 10/24/2019 | A | PASS |
Tell Riley
|
|
|
Special Inspection on site for reinforcement and concrete testing. Concrete scheduled for 6:30am. I will also take pictures for your reference and see what we can see when you arrive. Phone #: ###-#### Inspection requested via web by Travis Blackburn//pass pending specials//
|
BLD-Foundation | 10/3/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Tell Riley
|
|
|
Pouring stem walls at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//
|
BLD-Footing | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Tell Riley
|
|
|
2nd half of building footings//bar ok--ok to pour pending specials inspections//
|
BLD-Footing | 9/24/2019 | 9/25/2019 | 9/25/2019 | P | PART |
Tell Riley
|
|
|
Concrete is scheduled for 2pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//only half of the footing is complete//ok per plans//pending specials//
|