(13 PERMITS IN EPLAN UNDER BLD19-00526) (BUILDING J – VILLAGE EAST APARTMENTS – RESIDENTIAL) (PUD18-00042) (DRH18-00528) The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 39,944 square foot, 4 story apartment building (9,986 square foot 1st story, 9,986 square foot 2nd story, 9,986 square foot 3rd story, and 9,986 square foot 4th story) with a total of 32 dwelling units (8 on each story). Because there is an elevator in the adjacent building and all stories are connected to that building by a pedestrian walkway, all dwelling units on all stories are required to comply as Type B dwelling units (1 is also required to comply as Type A). Work is to include concrete footings, concrete stem walls between conditioned and unconditioned spaces, concrete pedestals, concrete slab on grade with thickened slab at interior bearing walls and R-10 perimeter slab edge insulation between conditioned and unconditioned spaces, 2x6 walls between conditioned and unconditioned spaces with R-20 cavity insulation and R-3.8 continuous insulation, wood columns, shear walls with gypsum panels or structural wood panels and hold downs, an unconditioned 1-hr fire-resistance-rated corridor on each story, two unconditioned 2-hr fire-resistance-rated exterior stairways, 1-hr dwelling unit separation walls between dwelling units, draftstops in the attic, 1-hr dwelling unit separation floors between dwelling units, engineered wood truss roof system with a structural wood panel roof deck and R-49 insulation installed on top of the ceiling with the attic vented to the outside, roof overbuilds, ladder and roof hatch to access roof top heat pumps, exterior windows, interior doors between conditioned and unconditioned spaces, exterior cementitious lap siding, exterior brick veneer, exterior stucco, guards, handrails, asphalt shingles, 3-ply roofing membrane at flat roof areas, roof drains and overflow drains, interior millwork, and interior finishes. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The design for the engineered wood trusses is a deferred submittal item. The fire sprinkler system is required to comply with NFPA 13-R (or NFPA 13) and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in7/13/20207/13/20207/13/2020PPART
DetailsTell Riley
Roof Phone #: ###-#### Inspection requested via web by Lee Scott//ok on most trusses//some trusses inwrong locatin and bearing points//lee will have truss fix for these trusses from manufacturer//
BLD-Wall Bracing7/9/20207/10/20207/10/2020APART
DetailsTell Riley
Hold downs Phone #: ###-#### Inspection requested via web by Lee Scott//one hold down on interior needs to be changed out for correct size//others appear to meet shcedule//
BLD-Framing/Rough-in7/9/20207/10/20207/10/2020APART
DetailsTell Riley
Roof framing Phone #: ###-#### Inspection requested via web by Lee Scott//north east block of building trusses//will need to check other 2 blocks// one girder installed in wrong direction//other truss bracing appears to be ok//
BLD-Wall Bracing6/10/20206/11/20206/11/2020PPART
DetailsTell Riley
Inspect floor to floor straps for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//exterior floor to floor strapping ok--north end 4 straps need to be changed to meet requirements//
BLD-Framing/Rough-in5/20/20205/20/20205/20/2020PPART
DetailsTell Riley
Inspect truss anchors (H2.5''s) at balcony beams for rated soffits to be hung and trusses at top of stairways for shaftliner assembly to go in. Phone #: ###-#### Inspection requested via web by Travis Blackburn//add hangers, nails in hangers as noted//truss fix was reviewed onsite for modified truss over elevator landing area//
BLD-Wall Bracing5/19/20205/19/20205/19/2020PPART
DetailsTell Riley
Shear panels only. Need to load the building a little before floor to floor straps Phone #: ###-#### Inspection requested via web by Travis Blackburn//nailing only on exterior and corridor//add nails as discussed on walk through//several areas in corridors//
BLD-Concrete1/13/20201/13/20201/13/2020PDEFR
DetailsTell Riley
Sorry forgot to add this inspection. We are pouring the corridor for building J today at 11. Thanks Phone #: ###-#### Inspection requested via web by Matt Perry//specials will be onsite//defer to special inspections//
BLD-Concrete1/7/20201/8/20201/8/2020APASS
DetailsTell Riley
Please inspect after 11am, we will be finished with set up and might have to cover the slab. Thanks Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials and elevated bar for clearances//
BLD-Concrete11/18/201911/19/201911/19/2019PPASS
DetailsTell Riley
The walls for building J are getting poured Wednesday about noon Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials and rebar clearances//
BLD-Footing11/12/201911/13/201911/13/2019APART
DetailsTell Riley
Pouring the footing for Building J tomorrow ( Wednesday) at 2pm. Phone #: ###-#### Inspection requested via web by Matt Perry//ok per plans pending specials//looked at footings for elevator as well--ok per details on structurals//