Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD19-00535
StatusIssued
Name ESI
Site Address 11916 W FAIRVIEW AVE
Project NameVillage East - Building L
Customer NumberBLD19-00526-00536, 538-539
ePlanReviewNo
Description
(13 PERMITS IN EPLAN UNDER BLD19-00526) (BUILING L – VILLAGE EAST APARTMENTS – RESIDENTIAL) (PUD18-00042) (DRH18-00528) The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 22,793 square foot, 4 story apartment building (5,959 square foot 1st story, 5,959 square foot 2nd story, 5,959 square foot 3rd story, and 4,916 square foot 4th story) with a total of 16 dwelling units (4 on each story). All dwelling units on the 1st story are required to comply as Type B dwelling units (one is also required to comply as Type A in Building G and in Building K). Since there is no elevator in this building, the dwelling units located on the 2nd, 3rd and 4th stories are not regulated for accessibility to the disabled. Work is to include concrete footings, concrete stem walls between conditioned and unconditioned spaces, concrete pedestals, concrete slab on grade with thickened slab at interior bearing walls and R-10 perimeter slab edge insulation between conditioned and unconditioned spaces, 2x6 walls between conditioned and unconditioned spaces with R-20 cavity insulation and R-3.8 continuous insulation, wood columns, shear walls with gypsum panels or structural wood panels and hold downs, an unconditioned 1-hr fire-resistance-rated corridor on each story, two unconditioned 2-hr fire-resistance-rated exterior stairways, 1-hr dwelling unit separation walls between dwelling units, draftstops in the attic, 1-hr dwelling unit separation floors between dwelling units, engineered wood truss roof system with a structural wood panel roof deck and R-49 insulation installed on top of the ceiling with the attic vented to the outside, roof overbuilds, ladder and roof hatch to access roof top heat pumps, exterior windows, interior doors between conditioned and unconditioned spaces, exterior cementitious lap siding, exterior brick veneer, exterior stucco, guards, handrails, asphalt shingles, 3-ply roofing membrane at flat roof areas, roof drains and overflow drains, interior millwork, and interior finishes. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The design for the engineered wood trusses is a deferred submittal item. The fire sprinkler system is required to comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall Bracing7/23/20207/23/20207/23/2020PPASS
DetailsTell Riley
Interior gype shear walls all floors . Phone #: ###-#### Inspection requested via web by Lee Scott//nailing ok on interior shear walls//
BLD-Other7/22/20207/23/20207/23/2020APART
DetailsTell Riley
Ok to cover drop ceilings levels 1 and 2 . Phone #: ###-#### Inspection requested via web by Lee Scott//drops ok to cover//lee will verify that mechanical is fire caulked on floor 2 and fire sprinkler mains into riser room are fire caulked//
BLD-Wall cover7/13/20207/14/20207/14/2020PPART
DetailsTony Young
Drop ceiling inspection on 3rd and 4th floors Phone #: ###-#### Inspection requested via web by Travis Blackburn// 3rd a nd 4th ok
BLD-Framing/Rough-in7/1/20207/2/20207/2/2020APART
DetailsTell Riley
Corridor cover inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//corridors ok//trades passed//fire caulk installed//
BLD-Energy code compliance6/26/20206/26/20206/26/2020PPART
DetailsTell Riley
INsulation inspection for 1st and 2nd floor approval for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//framing corrections made//stuff insulation around vent pipes//
BLD-Framing/Rough-in6/22/20206/23/20206/23/2020APART
DetailsTell Riley
Framing on 1st and 2nd floor for approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//add studs at locations marked//fire caulk where marked//address joist cut in unit 102//ok to insulate only//
BLD-Energy code compliance6/19/20206/19/20206/19/2020PPART
DetailsTell Riley
3rd and 4th floor for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok after plumbing is fire caulked as discussed//
BLD-Framing/Rough-in6/15/20206/16/20206/16/2020APART
DetailsTell Riley
Inspection on 3rd and 4th floor for approval to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate//need fire approval//add firecaulk as discussed//fix studs//shear ok//
BLD-Framing/Rough-in6/10/20206/11/20206/11/2020PPART
DetailsTell Riley
Inspect Holddowns at 1st floor and interior shear Phone #: ###-#### Inspection requested via web by Travis Blackburn//hold downs ok--tighten nut in one location//shear walls need nails added to meet 3" oc requirement--call back in and check floor to floor strapping all levels//
BLD-Framing/Rough-in6/8/20206/8/20206/8/2020PNR
DetailsTell Riley
Corridor framing inspection preliminary of framing Phone #: ###-#### Inspection requested via web by Travis Blackburn//add nails to hangers//addhorizontal hold down where missing//fire caulk penetrations//verify trades inspections approved//
BLD-Framing/Rough-in6/5/20206/5/20206/5/2020PPART
DetailsTell Riley
Sturctural inspection on trusses and hardware. Would also like to look at riser room on A to insulate and rock Phone #: ###-#### Inspection requested via web by Travis Blackburn//add scab to C3G trusses per truss docs//other trusses ok//
BLD-Framing/Rough-in6/3/20206/3/20206/4/2020PCANC
DetailsTell Riley
BLD-Framing/Rough-in6/2/20206/3/20206/3/2020ACANC
DetailsTell Riley
Inspection of truss bracing and plate fastening/HD''s Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD-Framing/Rough-in5/21/20205/21/20205/21/2020PPART
DetailsTell Riley
Prerock areas at exterior walls on 1st -3rd floors Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok when anchor bolts are added at first floor shear walls//
BLD-Framing/Rough-in3/26/20203/27/20203/27/2020APART
DetailsTell Riley
Framing inspection at breezeway ceiling to install shaftliner assembly to bottom of trusses Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok when H2.5s are installed//
BLD-Wall Bracing2/17/20202/18/20202/18/2020APART
DetailsTell Riley
Shear nail and hardware to install weather barrier, windows and soffit and fascia Phone #: ###-#### Inspection requested via web by Travis Blackburn//exterior nailing and strapping ok//
BLD-Wall Bracing2/13/20202/14/20202/14/2020PNR
DetailsTell Riley
Exterior shear inspection including hardware if time allows Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to renail the fist 2 stories, nails are over driven//
BLD-Concrete10/29/201910/30/201910/30/2019PPART
DetailsTell Riley
Slab for building L getting poured Thursday at 6:30am Phone #: ###-#### Inspection requested via web by Matt Perry//blankets onsite//pour will be early in the am//pending special inspection and approval//
BLD-Concrete10/9/201910/14/201910/14/2019APART
DetailsTell Riley
We are pouring the stem walls for Building L (This building at 1pm. Phone #: ###-#### Inspection requested via web by Matt Perry//need to meet bar clearances//specials will be completed//ok when specials pass//
BLD-Footing10/8/201910/8/201910/8/2019PPASS
DetailsTell Riley
Concrete pour at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//footings ok per plans//pending specials....//