BLD-Final | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter
|
FIRE-Final Inspection | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Zach Carter
|
FIRE-Final Inspection | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | FAIL |
Jim Page
|
|
|
Exit signage needs to match what was submitted on city approved drawings, provide code compliant hardware on NW exit door, riser room is not 1 hour fire rated due to multiple holes in wall, provide and install knox box. Mount fire extinguishers at max 48" to mechanism as discussed. Still need to verify emergency operation of all emergency lights. FIR permit for fire sprinklers must be finaled before life safety can be completed. GR
Phone #: ###-#### Inspection requested via web by Zach Carter
|
BLD-Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Zach Carter Inspection cancelled from web by: Zach Carter
|
BLD-Final | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//need fire life safety, sprinkler and fire alarm finals// will need to reshedule//
|
BLD-Framing/Rough-in | 12/23/2020 | 12/24/2020 | 2/5/2020 | P | PART |
Tell Riley
|
|
|
Per Tell, framing inspection put on Foundation permit. Switching it to BLD19-00843 2-5-2020 // new GB over existing framing//insulation ok, vapor barrier installed//no electrical or plumbing//
|
BLD-Conference | 12/12/2019 | 12/16/2019 | 12/16/2019 | A | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//site walk through//accesible ramp to steep on outside of building--discussed options to make compliant//accessible ramp inside filled with insulation-talk with Troy about depth of fill//will need framing for tall building area prior to cover//
|
BLD-Conference | 11/12/2019 | 11/15/2019 | 11/15/2019 | A | DONE |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Zach Carter//discussed RFI for ramp --approved as is by engineer for structural//discussed climbing wall structures and verifiying permits and special inspections//
|
FIRE-Conference | 11/12/2019 | 11/14/2019 | 11/14/2019 | P | DONE |
Troy Cobbley
|
|
|
We discussed possible combustible concealed spaces caused by the climbing wall construction. Phone #: ###-#### Inspection requested via web by Zach Carter
|
BLD-Framing/Rough-in | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PART |
Tell Riley
|
|
|
Zach Phone #: ###-####//need to provide mod for construction changes to ramp//vestibule, bathrooms ok when fire sprinklers have passed--discussed with Troy and advised Zach to schedule fire conference for areas behind rock walls//
|
BLD-Conference | 7/22/2019 | 7/24/2019 | 7/24/2019 | A | DONE |
Tell Riley
|
|
|
Zack Phone #: ###-####//discuss project and advised Zack to submit plan changes to plan review for approval//
|
BLD-Foundation | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Pending special inspection...
|
BLD-Footing | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | PART |
Tell Riley
|
|
|
Zach Phone #: ###-####//concrete already poured//specials were completed to epoxy, rebar and concrete//
|