BLD-Framing/Rough-in | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Jim Storey
|
|
|
Chris *screened Phone #: ###-#### bathrooms 2nd floor ok to cover// gyp ceillings 2nd floor ok to cover// wall framing 1st floor ok
|
BLD-Framing/Rough-in | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PASS |
Jim Storey
|
|
|
Screened- Jeff Phone #: ###-#### walls/soffts and hard lids ok to cover 1st floor phase 2
|
BLD-Framing/Rough-in | 7/21/2020 | 7/21/2020 | 7/21/2020 | P | PASS |
Jim Storey
|
|
|
Nate - */Screened no symptoms in the last 2 weeks per Nate. Able to wear masks*/ Phone #: ###-####
|
BLD-Framing/Rough-in | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### center space.
|
BLD-Framing/Rough-in | 6/26/2020 | 6/26/2020 | 6/26/2020 | P | PASS |
Jim Storey
|
|
|
Nathan Phone #: ###-#### 2nd floor ok
|
BLD-Final | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PASS |
Jim Storey
|
|
|
screened // Nathan Phone #: ###-#### temp ok 1st floor phase one// conf rm on hold until haedware and sinage complet.
|
FIRE-Final Inspection | 5/21/2020 | 5/27/2020 | 5/27/2020 | P | PART |
Jim Page
|
|
|
Final life fire safety inspection for TCO phase 1 level 1 is complete, signature for TCO phase 1 level 1 provided on permit sign off card.
Screened- Nathan Phone #: ###-####
|
BLD-Final | 5/13/2020 | 5/14/2020 | 5/14/2020 | A | PASS |
Jim Storey
|
|
|
Nate - requesting TCO Phone #: ###-#### phase 1 2nd floor ok for occupance.
|
FIRE-Final Inspection | 5/11/2020 | 5/13/2020 | 5/13/2020 | P | PART |
Jim Page
|
|
|
Final life fire safety inspection for TCO phase 1 is complete, signature for TCO phase 1 provided on permit sign off card.
Nathan - phase one level 2 Phone #: ###-####
|
FIRE-Alarm Testing | 5/13/2020 | 5/13/2020 | 5/13/2020 | P | CANC |
Jim Page
|
|
|
Fire alarm testing notes have been entered under FIR20-00166, this request is cancelled.
Nathan Phone #: ###-####
|
BLD-Conference | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PART |
Jim Storey
|
|
|
screened // Nate Phone #: ###-#### east 90 min fire door needs latch / remove office door.
|
BLD-Framing/Rough-in | 4/28/2020 | 4/29/2020 | 4/29/2020 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### exterior south vestabui.
|
BLD-Ceiling Grid Inspection | 4/13/2020 | 4/14/2020 | 4/14/2020 | A | PART |
Jim Storey
|
|
|
Nate Phone #: ###-####
|
FIRE-Conference | 3/23/2020 | 3/23/2020 | 3/23/2020 | P | DONE |
Jim Page
|
|
|
Fire conference is complete.
Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 3/6/2020 | 3/9/2020 | 3/9/2020 | A | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### hardlids 1st floor ok// beam in conf. rm ok.
|
BLD-Foundation | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### si report pending
|
BLD-Framing/Rough-in | 3/3/2020 | 3/4/2020 | 3/4/2020 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### restarooms phase 3 ok to cover all/ b2 east ceillings ok to fill and hard lids at stair and b2 ok to cover.
|
BLD-Framing/Rough-in | 2/24/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-####// area a2 ceillings hard and drop in ok to cover.
|
BLD-Foundation | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PASS |
Jim Storey
|
|
|
pouring at 3pm- Nate Phone #: ###-####
|
BLD-Footing | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PASS |
Jim Storey
|
|
|
rebar-Nathan Phone #: ###-####
|
BLD-Framing/Rough-in | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Jim Storey
|
|
|
Nathan Phone #: ###-#### restarooms backing ft ok to cover//
|
BLD-Framing/Rough-in | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Jim Storey
|
|
|
Nate Phone #: ###-#### walls and soffits 1st and 2nd floors phase 1 ok
|